Quarterly Report

For the three months ended 30 September 2021

(figures are unaudited and in US$ except where stated)

Q1 in line with expectations as organic growth agenda advanced

  • September quarter in line with expectations and on track to meet annual guidance1,2
    1. Gold production of 396koz3 and copper production of 25kt
    1. All-InSustaining Cost (AISC) of $1,270/oz3
    1. AISC margin of $406/oz4
    1. Gold and copper production expected to increase in the December quarter2
  • Advancing Newcrest's global organic growth portfolio
    1. Newcrest recently released the findings of the Red Chris Block Cave, Havieron Stage 1, Lihir Phase 14A and Cadia PC1-2Pre-Feasibility Studies (PFS)5:
      • All four organic growth options estimated to deliver an IRR of 16% or higher6,7
      • Projected 50% reduction in Newcrest's AISC per ounce by FY306,7
      • Projected gold production of approximately 2Moz per annum until at least FY306,7
      • Projected material growth (+37%) in copper production by FY30, sourced exclusively from Tier 1 jurisdictions6,7
      • Lihir projected to become a 1Mozpa+ gold producer for at least 10 years from FY246,8
      • Projected multi-decade asset lives at Cadia, Lihir and Red Chris
      • Newcrest intends to fund all four projects through operating cash flow and existing liquidity
  1. Exploration decline development advancing well at Red Chris and Havieron
  1. West Dome Stage 5 cutback underway, supporting the continuity of operations at Telfer2
  1. Commissioning of the Moly Plant at Cadia ongoing, with first production expected in November 20212

Newcrest Managing Director and Chief Executive Officer, Sandeep Biswas, said, "Newcrest's production in the September quarter was in line with our expectations and reflects the replacement and upgrade of the SAG mill motor at Cadia, the completion of the re-bricking of Autoclave 4 at Lihir and other planned maintenance shutdowns across the Group which is consistent with prior years. We expect gold and copper production to increase in the December quarter with lower planned shutdown activities and completion of the SAG mill motor replacement and we remain on track to meet our FY22 guidance."

"We were very pleased to take a significant step forward in advancing our organic growth agenda in October. The findings of the Red Chris Block Cave, Havieron Stage 1, Lihir Phase 14A and Cadia PC1-2Pre-Feasibility Studies demonstrate the depth and quality of our global organic growth portfolio and create an exciting pathway for our future. Newcrest expects to achieve very attractive rates of return on each project, with strong growth in copper production and a reduction of more than 50% in our already low All-In Sustaining Cost expected over the next decade. These Studies outlined our base case projections and have the potential for further upside to deliver strong gold and copper production for decades to come."

"This is a genuinely exciting time for Newcrest and highlights our commitment to deliver superior returns to our shareholders. We look forward to providing further updates as we progress these compelling opportunities." said Mr Biswas.

Newcrest Mining Limited - Level 8, 600 St Kilda Road, Melbourne - Quarterly Report to 30 September 2021

1

Overview

Gold production was 27% lower than the prior period9 mainly driven by lower mill throughput rates at Cadia, Lihir and Telfer. As foreshadowed in the June 2021 quarterly report, Cadia's mill capacity was limited by the replacement and upgrade of the SAG mill motor resulting in lower gold production during the period. Mill throughput rates were also lower at Lihir and Telfer following planned and unplanned shutdown activities.

Newcrest's AISC for the September 2021 quarter of $1,270/oz3 was higher than the prior period, reflecting lower gold and copper sales volumes, higher production stripping at Lihir with increased waste mined and a lower realised copper price. This was partially offset by the benefit of a weakening Australian dollar against the US dollar on operating costs.

Injury rates were higher than the prior period at Cadia, Telfer and Red Chris. Newcrest is focused on visible safety leadership supported by NewSafe and the Critical Control Management (CCM) program to ensure employees and contractors across all sites are using the appropriate safety practices to maintain a safe and healthy workplace.

Metric

Sep

Jun

FY21

FY22 Guidance10

2021 Qtr

2021 Qtr

Group3

- gold

oz

396,214

542,332

2,093,322

1,800

- 2,000koz

- copper

t

24,527

38,370

142,724

125 - 130kt

- silver

oz

174,555

270,797

944,521

Cadia

- gold

oz

109,005

194,757

764,895

540

- 610koz

- copper

t

15,213

28,105

106,402

85 - 95kt

Lihir

- gold

oz

141,089

176,341

737,082

700

- 800koz

Telfer

- gold

oz

100,993

125,603

416,138

390

- 440koz

- copper

t

3,838

4,685

13,177

~15kt

Red Chris11

- gold

oz

10,674

10,815

45,922

40

- 42koz

- copper

t

5,475

5,580

23,145

23 - 25kt

Fruta del Norte3,12

- gold

oz

34,452

34,816

129,285

120

- 135koz

Fatalities

Number

0

0

0

TRIFR13

mhrs

3.8

1.9

2.3

All-In Sustaining Cost3,14

$/oz

1,270

799

911

All-In Cost15

$/oz

1,949

1,242

1,278

All-In Sustaining Cost margin4,14

$/oz

406

975

876

Realised gold price16

$/oz

1,722

1,780

1,796

Realised copper price16

$/lb

4.24

4.42

3.66

Realised copper price16

$/t

9,348

9,744

8,069

Average exchange rate

AUD:USD

0.7354

0.7700

0.7467

Average exchange rate

PGK:USD

0.2846

0.2843

0.2854

Average exchange rate

CAD:USD

0.7944

0.8124

0.7789

All figures are shown at 100%, except for Red Chris which is shown at Newcrest's 70% share and Fruta del Norte which is shown at Newcrest's 32% attributable share through its 32% equity interest in Lundin Gold Inc.

Newcrest Mining Limited - Level 8, 600 St Kilda Road, Melbourne - Quarterly Report to 30 September 2021

2

Operations

Cadia, Australia

Highlights

Metric

Sep

Jun

FY21

FY22

2021 Qtr

2021 Qtr

Guidance10

TRIFR13

mhrs

9.2

2.0

6.1

Total production

- gold

oz

109,005

194,757

764,895

540 - 610koz

- copper

t

15,213

28,105

106,402

85 - 95kt

Head Grade

- gold

g/t

0.82

0.92

0.95

- copper

%

0.35

0.40

0.40

Sales

- gold

oz

105,541

201,494

766,118

- copper

t

14,886

29,039

105,444

All-In Sustaining Cost

$/oz

203

(377)

(109)

All-In Sustaining Cost margin

$/oz

1,519

2,157

1,905

Cadia TRIFR of 9.2 recordable injuries per million hours was higher than the prior period, mainly driven by hand injuries. Improvement initiatives have been implemented at site to address rising injury rates, supported by visible safety leadership.

Cadia's gold production of 109koz was 44% lower than the prior period due to lower mill throughput and lower gold head grade, partially offset by higher recovery. As highlighted in the June 2021 quarterly report, mill throughput rates were limited by the replacement and upgrade of the SAG mill motor which commenced in early July 2021. Newcrest has implemented a SAG bypass for the duration of the SAG mill motor replacement and Concentrator 1 has been operating at ~60% of its normal capacity. Replacement of the SAG mill motor is progressing well and is expected to be completed in November 20212.

The lower gold head grade in the period was in line with expectations and is expected to increase in the December 2021 quarter2.

Cadia's AISC of $203/oz was higher than the record AISC of negative $377/oz achieved in the prior period. This was predominantly driven by lower gold and copper sales volumes and a lower realised copper price, partially offset by the favourable impact on operating costs from the weakening Australian dollar against the US dollar.

In August 2021, the Newcrest Board approved the Cadia PC1-2 PFS, enabling the commencement of the Feasibility Study and Early Works Program. The PFS updates and defines a significant portion of Cadia's future mine plan, with the development of PC1-2 accounting for ~20% of Cadia's current Ore Reserves. The study delivers attractive returns with an optimised mine design expected to deliver higher gold and copper grades and enable the deferral of capital expenditure in the medium term.

In summary, the Study identified the following (assuming a gold price of $1,500/oz, copper price of $3.30/lb and AUD:USD of 0.75)5,6,17,18,21:

  • Internal Rate of Return (IRR) of 22%, with a 4.4 year payback19
  • Net Present Value (NPV) of A$2.0 billion (US$1.5 billion)20
  • The Feasibility Study is expected to be completed in the second half of CY222

Applying economic assumptions closer to prevailing rates (i.e. a gold price of $1,750/oz, copper price of $4.15/lb and AUD:USD exchange rate of 0.73) results in an estimated IRR of 28% and an estimated NPV of US$2.3 billion5,6,17,18,21.

See release titled "Cadia PC1-2 Pre-FeasibilityStudy delivers attractive returns"dated 19 August 2021 for further information.

Commissioning of the Molybdenum Plant (Moly Plant) is ongoing, with first production expected in November 20212. The Moly Plant will deliver an additional revenue stream for Cadia in the form of a molybdenum concentrate which will be recognised as a by-product credit to AISC.

Newcrest Mining Limited - Level 8, 600 St Kilda Road, Melbourne - Quarterly Report to 30 September 2021

3

Lihir, Papua New Guinea

Highlights

Metric

Sep

Jun

FY21

FY22

2021 Qtr

2021 Qtr

Guidance10

TRIFR13

mhrs

0.8

0.4

0.3

Production

- gold

oz

141,089

176,341

737,082

700 - 800koz

Head Grade

- gold

g/t

2.32

2.45

2.40

Sales

- gold

oz

135,582

197,651

773,146

All-In Sustaining Cost

$/oz

1,986

1,50414

1,391

All-In Sustaining Cost margin

$/oz

(264)

27614

405

Gold production of 141koz was 19% lower than the prior period due to lower mill throughput, grade and recovery. Lower mill throughput rates were the result of planned major maintenance shutdowns of Autoclave 4, Autoclave 2, mills and oxygen plant and associated equipment. Mill throughput is expected to improve in the December 2021 quarter2. Head grade was lower than the prior period as expected in the mine plan and recoveries were lower as a result of lower performing stockpile feed and planned maintenance shutdowns.

Mining rates were 29% higher than the prior period resulting from the mining improvement program. Higher mining rates at Lihir are expected to continue for the remainder of the year.

Lihir's AISC of $1,986/oz was 32% higher than the prior period driven by lower gold sales volumes, additional production stripping costs due to a 27% increase in waste tonnes mined primarily from Phase 16, and higher sustaining capital expenditure. Site operating costs were also higher during the period mainly driven by plant shutdown costs.

In October 2021, the Newcrest Board approved the Lihir Phase 14A PFS enabling the commencement of the Feasibility Study and Early Works Program. The Study confirms Lihir's pathway to becoming a 1 million ounce plus producer for at least 10 years from FY248. It also highlights the potential for Phase 14A wall support techniques to be applied to future cutbacks at Lihir, unlocking additional value.

In summary, the Phase 14A Study has identified the following (assuming a gold price of $1,500/oz)5,6,22,23:

  • IRR of 37% (real, after tax), with a 2.6 year payback19
  • NPV of $284 million20
  • Increase to Ore Reserves by 1Moz to 23Moz as at 30 June 202124
  • The Feasibility Study is expected to be completed in the fourth quarter of FY222

Applying economic assumptions closer to prevailing rates (i.e. a gold price of $1,750/oz) results in an estimated IRR of 47% and an estimated NPV of $365 million5,6,22,23.

See release titled "Lihir PFS supports gold production growth to 1Mozpa+ from FY24"dated 12 October 2021 for further information.

Newcrest Mining Limited - Level 8, 600 St Kilda Road, Melbourne - Quarterly Report to 30 September 2021

4

Lihir - Material Movements

Ore Source

Metric

Sep

Jun

FY21

2021 Qtr

2021 Qtr

Ex-pit crushed tonnes

kt

604

819

5,379

Ex-pit to stockpile

kt

1,037

364

3,283

Waste

kt

8,601

6,776

24,805

Total Ex-pit

kt

10,242

7,959

33,467

Stockpile reclaim

kt

1,781

2,229

7,752

Stockpile relocation

kt

2,831

3,164

12,493

Total Other

kt

4,612

5,393

20,244

Total Material Moved

kt

14,854

13,352

53,712

Lihir - Processing

Equipment

Metric

Sep

Jun

FY21

2021 Qtr

2021 Qtr

Crushing

kt

2,450

3,048

13,130

Milling

kt

2,584

3,010

12,792

Flotation

kt

2,107

2,191

9,876

Total Autoclave

kt

1,354

1,722

6,954

Newcrest Mining Limited - Level 8, 600 St Kilda Road, Melbourne - Quarterly Report to 30 September 2021

5

This is an excerpt of the original content. To continue reading it, access the original document here.