March 16, 2022

To whom it may concern

Company name: Representative:Okamura Corporation Masayuki Nakamura

Representative Director, President and Chief Executive Officer

(Code: 7994, Listing: First Sections of Tokyo Stock Exchange)Contact:

TEL:Naoki Kono, Managing Director and Executive Officer, CFO +81-(0)3-5539-6465

Notice Concerning the Construction of a New Plant Building

The Company hereby announces that its Board of Directors has resolved at its meeting held today that the Company will construct a new plant building in the site of the Tsukuba Plant (Tsukuba, Ibaraki Prefecture).

In its Midterm Management Plan, the Okamura Group identified as a group-wide effort a supply chain reform to suit manufacturing a wide variety of products flexibly in order to respond to increasingly diverse customer needs and changing market trends.

The Company has set aside 40 to 50 billion yen to fund strategic investments, including those for strengthening existing businesses and creating new businesses and those for addressing priority issues, for the three-year period from 2020 to 2022. This construction is part of such investments.

  • 1. Purpose of the construction of a new plant

    The Office Furniture business is experiencing strong demand for office renovation to support new work styles arising from, for example, the modification of central office functions as a result of the spread of hybrid workplaces caused by rapid changes in social values and lifestyles under the COVID-19 pandemic. We expect that the diversification of needs and changes in trends will further accelerate going forward.

    By constructing a new plant building, the Company will create a flexible production system for new products as well as its main products to respond to changes in the market. The new plant building will also be instrumental in the promotion of ongoing cost reductions across the entire supply chain by improving in-house production ratio and enhancing the plant warehousing function.

  • 2. Outline of the new plant building

    Name

    Tsukuba New Plant Building

    Location

    Techno-Park Toyosato, 1-2-2 Midorigahara, Tsukuba, Ibaraki Prefecture

    Building area

    23,000 m2

    Gross floor area

    44,100 m2

    Structure

    Steel, 2F above ground

    Main facilities

    Powder coating line, sheet metal automatic processing facilities, etc.

    Total investment

    11.5 billion yen

    Funding plan

    Own funds

    Items to be produced

    Modular storage furniture, work booths, various partitions, fixtures for use at medical and laboratory facilities, fixtures for use at educational facilities, etc.

    (Reference) Tsukuba Plant The Tsukuba Plant started operation in 1991 with a site area (land) of 99,456 m2. As a main plant of the Office Furniture business, it produces mainly storage furniture.

  • 3. Timeline (schedule)

    Start of construction

    July 2022

    Completion of construction

    August 2023

    Start of operation

    November 2023

  • 6. Future outlook

    The impact of this construction on the business performance of the Company will be insignificant. The Company will disclose any necessary matters promptly as they arise in the future.