Panoramic Resources Limited provided an update on the advancement of operational activities at the Savannah Nickel Project to support the target of first nickel-copper-cobalt concentrate shipment in December 2021. Key Points: Processing contractor Primero has fully mobilised to site and has successfully commissioned the Savannah processing plant three weeks ahead of schedule; Plant ore feed is being sourced from the +120kt ore stockpile generated since mining operations restarted; First nickel-copper-cobalt concentrate has been produced from the plant and is being stockpiled at site; Trucking of concentrate from site to the Wyndham Port is planned to commence next week; First shipment of concentrate is expected to leave Wyndham port in December 2021. The ~1Mtpa processing plant at Savannah has been successfully commissioned three weeks ahead of schedule, following the completion of requisite preparatory works by Primero's maintenance crew. As previously announced, Primero had partially mobilised to site to ensure operational readiness at the plant, which upon completion, allowed for full mobilisation of Primero's operating crews and the commencement of 24/7 ore processing to begin. The crushing, milling and flotation circuits, and tailings processing have achieved operational stability with concentrate production underway. Concentrate haulage from site to Wyndham Port is planned to commence next week, with haulage contractor Cambridge Gulf Limited having already recruited a local workforce for concentrate haulage. Primero's recruitment process ahead of the restart has been extremely successful given the current labour environment. All management and technical roles have been filled and 95% of the recruited workforce are WA-based employees, with the remaining employees being Northern Territory-based.