Pantheon Resources Plc provided the following operational update on the Alkaid #2 well. Operational update - Alkaid #2: As previously announced, the lateral section of the Alkaid #2 wellbore is partially blocked with approximately 1,000 feet of frac sand which (i) has restricted tested flow rates due to the lack of contribution from the blocked section, and (ii) has necessitated a more conservative testing protocol in order to not exacerbate the blockage, which has resulted in a slower 'cleanup phase'. Encouragingly, despite the blockage, the well is flowing naturally into Pantheon's recently commissioned permanent production facilities located on the Dalton Highway at a rate of over 500 barrels per day (bpd) of hydrocarbon liquids which includes oil, condensate and natural gas liquids (NGL's), as well as significant natural gas, from an estimated 4,000 ft of lateral.

Importantly, it is estimated that the well is still less than 40% of the way through cleanup phase, so potential exists for these rates to further improve. Crude oil is processed on location and oil sales are underway. To date over 7,000 barrels of 38-41 degree API oil has been trucked and sold into the Trans Alaska Pipeline System.

This oil is lighter than existing North Slope oil production and hence a welcome addition to the production stream. A proportion of the gas production is used to generate power across all the facilities that are now electrically powered and operational, reducing flaring and providing cost savings to operations at this location. Production: At this early clean up stage, Alkaid #2 is delivering hydrocarbon liquid rates near expectations over the 4,000 ft unblocked section, with gas rates well above original prognosis.

Sustained daily production over more than the last 30 days has averaged over 500 barrels per day of hydrocarbon liquids, of which circa 200 bpd of crude oil and over 300 bpd being condensate and NGLs, all of which can be sold either by blending into the pipeline or trucking to an Alaskan refinery. Gas rates are above 2.5 mmcfd which is higher than originally anticipated, however this is not believed to be from a gas cap but coming out of solution near the well bore. This is not considered a long term problem as excess gas could be reinjected into the reservoir for pressure maintenance.

This combined hydrocarbon deliverability to date confirms the forecasted reservoir properties and highlights the potential deliverability of the Alkaid reservoir. The Company is confident there is upside above these rates as it is apparent that only a portion of the completed wellbore is contributing to the production stream; and it is estimated that the well has produced to date less than 40% of the volume of frac fluid used in the stimulations. Sand: As previously announced, the flow rate is restricted by the accumulation of sand in the horizontal portion of the well bore also slows down well cleanup.

This is not uncommon in long horizontal wells that have been treated with multi stage fracture stimulations. With the correct equipment, removing the sand and cleaning the well is a simple operation which is currently planned for January. The sand blockage in the well bore was identified early in the production test, however no winterized workover rig was available which prohibited the removal of the tubing and a proper clean out at that time.

Instead, a coiled tubing unit ("CTU") was used to conduct a through-tubing cleanout, but was unable to reach the full well depth and hence was partially successful with more than 1,000 ft remaining blocked and untouched by the CTU clean out. A rig is available in January to clean out the entire well bore and is expected to open the entirety of the lateral allowing the full potential of the well to be revealed and at the same time accelerating the clean up phase. In advance of the clean out the Company plans to shut in and perform reservoir diagnostics, a normal oilfield practice, to gather additional data.