NEWS RELEASE | 29 January 2021

DECEMBER 2020 QUARTERLY REPORT

Prairie Mining Limited (Prairie or the Company) is pleased to present its Quarterly Report for the period ending 31 December 2020.

HIGHLIGHTS

  • International arbitration claims (Claim) against the Republic of Poland under both the Energy Charter Treaty and the Australia-Poland Bilateral Investment Treaty (Treaties) ongoing with the proceedings having now been constituted and a quantum expert being appointed by the Company during the quarter.
    • Prairie alleges that the Republic of Poland has breached its obligations under the Treaties through its actions to block the development of the Company's Jan Karski and Debiensko mines in Poland.
    • The Republic of Poland's actions have deprived Prairie of the entire value of its investments in Poland.
    • Claim for the damages may include but is not limited to the value of Prairie's historical expenditure in developing both the Jan Karski and Debiensko mines, lost profits and damages, which is linked to the net present value of both mines, and accrued interest related to any damages.
  • The Company's Claim against the Republic of Poland will be prosecuted through an established and enforceable legal framework with both parties agreeing to apply the United Nations Commission on International Trade Law Rules (UNCITRAL) to the proceedings.
  • The Company is well funded to pursue the Claim with the US$12.3 million Litigation Funding Agreement (LFA) in place and currently being drawn down to cover legal, tribunal and external expert costs and defined operating expenses associated with the Claim.
  • Prairie continues its efforts to identify and assess other suitable new business opportunities, focused on the resources sector. The Company will make announcements to the market as appropriate.

Enquiries

Prairie Mining Limited

+44 20 7478 3900

Ben Stoikovich, Chief Executive Officer

info@pdz.com.au

Sapan Ghai, Head of Corporate Development

Kazimierz Chojna, Commercial Officer

This announcement as been authorised for release by the Company's Chief Executive Officer, Mr Ben Stoikovich.

Prairie Mining Limited | LSE / ASX / GPW: PDZ | ABN: 23 008 677 852 | www.pdz.com.au

LONDON Unit 3C, 38 Jermyn Street | London | SWY1 6DN | T: +44 207

478 3900

PERTH Level 9, 28 The Esplanade, Perth WA 6000 | T: +61 8 9322 6322 | F:

+61 8 9322 6558

WARSAW Wiejska 17/11 | Warsaw | 00-480

DISPUTE WITH POLISH GOVERNMENT

The Company's Claim against the Republic of Poland is being prosecuted through an established and enforceable legal framework, with Prairie and Poland agreeing to apply the UNCITRAL rules to the proceedings.

During the quarter, the proceedings for the Claim were constituted while the Company appointed a quantum expert for and considered other expert proposals and continued with document collation for the Claim.

Prairie's claim for compensation may include, but will not be limited to:

  • The value of Prairie's historic expenditure in developing both the Jan Karski and Debiensko mines;
  • Lost profits and damages that the Company has suffered as a result of Poland's acts and omissions which have resulted in the expropriation of both the Jan Karski of Debiensko mines, which is linked to the considerable Net Present Value of both mines at the time of Poland's international treaty breaches; and
  • Accrued interest related to any damages award and all costs associated with pursuing the Claims to Arbitration.

The Company is not able to make any further comment in relation to the potential quantum of any claim for compensation at this point. Please refer to ASX announcements dated 26 April 2018, 28 May 2018, 18 January 2019, 13 February 2019, 4 April 2019 and 31 December 2019 for further details regarding the Company's dispute with the Republic of Poland.

In July 2020, the Company announced it had executed a LFA for US$12.3 million with LCM. The facility is currently being drawn down to cover legal, tribunal and external expert costs and defined operating expenses associated with the Claim.

In September 2020, Prairie announced that it had formally commenced with the Claim by serving the Notices of Arbitration against the Republic of Poland.

Prairie's dispute alleges that the Republic of Poland has breached its obligations under the applicable Treaties through its actions to block the development of the Company's Jan Karski and Debiensko mines in Poland which effectively deprives Prairie of the entire value of its investments in Poland.

In February 2019, Prairie formally notified the Polish Government that there exists an investment dispute between Prairie and the Polish Government. Prairie's notification called for prompt negotiations with the Government to amicably resolve the dispute and indicated Prairie's right to submit the dispute to international arbitration in the event of the dispute not being resolved amicably. The Company remains open to resolving the dispute with the Polish Government amicably. However, as of the date of this report, no amicable resolution of the dispute has occurred, since the Polish Government has declined to participate in discussions related to the dispute and accordingly the Company has formerly submitted its Claim as discussed above.

Prairie's investment dispute with the Republic of Poland is not unique, with international media widely reporting that the political environment and investment climate in Poland has deteriorated since the change in Government in 2015. As a result, there are a significant number of International Arbitration claims being bought against Poland in the natural resources and energy sectors with damages claims ranging from US$120 million to over US$1.3 billion and includes Bluegas NRG Holding (Gas), Lumina Copper (Copper) and InvEnergy (wind farms).

Background to the Jan Karski Mine

The Jan Karski Mine (Jan Karski) is a large scale semi-soft coking coal project located in the Lublin Coal Basin in south east Poland. The Lublin Coal Basin is an established coal producing province which is well serviced by modern and highly efficient infrastructure, offering the potential for low capital intensity mine development. Jan Karski is situated adjacent to the Bogdanka coal mine which has been in commercial production since 1982 and is the lowest cost hard coal producer in Europe.

Key benefits previously identified for the local community and the Lublin and Chelm regions which would have been associated with the development, construction and operation of Jan Karski were recognised as the following:

2

  • creation of 2,000 direct employment positions and 10,000 indirect jobs for the region once operational;
  • increasing skills of the workforce through the implementation of International Standard training programmes;
  • stimulating the development of education, health services and communications within the region; and
  • building a mine that creates new employment for generations to come and career paths for families to remain in the region.

In March 2016, Prairie released the results of a JORC compliant Pre-Feasibility Study (PFS) for Jan Karski prepared by independent international mining consultancies Golder Associates and Royal HaskoningDHV. The PFS demonstrated the technical viability and robust economics of Jan Karksi to be developed as a large-scale long life strategic coal supplier. Further details about the PFS are contained in the Company's announcement dated 8 March 2016.

Background to the Debiensko Mine

The Debiensko Mine (Debiensko), is a premium hard coking coal project located in the Upper Silesian Coal Basin in the south west of the Republic of Poland. It is approximately 40 km from the city of Katowice and 40 km from the Czech Republic.

Debiensko is bordered by the Knurow-Szczyglowice Mine in the north west and the Budryk Mine in the north east, both owned and operated by Jastrzębska Spółka Węglowa SA, Europe's leading producer of hard coking coal.

The Debiensko mine was historically operated by various Polish mining companies until 2000 when mining operations were terminated due to a major government led restructuring of the coal sector caused by a downturn in global coal prices. In early 2006 New World Resources Plc acquired Debiensko and commenced planning for Debiensko to comply with Polish mining standards, with the aim of accessing and mining hard coking coal seams. In 2008, the Polish Ministry of Environment (MoE) granted a 50-year mine license for Debiensko.

In October 2016, Prairie acquired Debiensko with a view that a revised development approach would potentially allow for the early mining of profitable premium hard coking coal seams, whilst minimising upfront capital costs.

In March 2017, Prairie released the results of a JORC compliant Scoping Study prepared by independent international mining consultancy Royal HaskoningDHV. The Scoping Study demonstrated the technical viability and robust economics for the fully permitted Debiensko mine to be a large scale, lowest cost and long life premium hard coking coal supplier. Further details of the Scoping Study care contained in the Company's announcement dated 16 March 2017.

CORPORATE

Busines Development

A number of opportunities have been reviewed during the quarter, and the Company will continue in its efforts to identify and acquire suitable new business opportunities. The Company is currently focusing on new opportunities in the resources sector.

However, no agreements have been reached or licences granted and the Company is not able to assess the likelihood or timing of a successful acquisition or grant of any opportunities.

Balance Sheet

At 31 December 2020, the Company is in a strong financial position to pursue the Claim and continue with business development activities with the US$12.3 million LFA and cash reserves of A$5.8 million.

3

Forward Looking Statements

This release may include forward-looking statements. These forward-looking statements are based on Prairie's expectations and beliefs concerning future events. Forward looking statements are necessarily subject to risks, uncertainties and other factors, many of which are outside the control of Prairie, which could cause actual results to differ materially from such statements. Prairie makes no undertaking to subsequently update or revise the forward-looking statements made in this release, to reflect the circumstances or events after the date of that release.

4

This is an excerpt of the original content. To continue reading it, access the original document here.