• The approved project is aimed at replacing the boiler at Nevinnomysskaya GRES
  • After modernization commissioning is scheduled for the first quarter of 2022

MOSCOW, June 7th, 2019 - According to the results of the decision adopted by the Government Commission on the electric power development, Nevinnomysskaya GRES of PJSC Enel Russia was selected among the projects for modernization of thermal generation following the results of the first competitive selection for 2022- 2024.

The projects were selected on the basis of the framed criteria developed by the Ministry of Energy, which takes into account solutions for environmental problems, importance of the plant in the heat supply, efficiency of the project in terms of cost for consumers, technical condition of the power plant, and innovative technical solutions in the project.

According to the results of the project outtake, the generating companies assume the obligation to deliver the power for the period of 16 years, and to use localized equipment in the modernization projects, therefore investing money in the Russian energy mechanical engineering manufacture.

The project of modernization for Nevinnomysskaya GRES includes refurbishment of the boiler № 5 with the capacity of 480 t/h, which is technologically connected with 50 MW turbine № 4. The demand index for generating equipment presented in the project is more than 0.9. Commissioning after modernization is scheduled for the first quarter of 2022.

The approved by the Commission capex of the project will amount to 13 023.7 roubles per kW.