Reabold Resources Plc provided an update on the 2020 Work Program on the Parta Licence Area, onshore Romania. The Work Program is planned by Danube Petroleum Limited ("Danube"), which has a 100% interest in the Parta Sole Risk Area and will have a 50% interest in the Parta Exploration Licence. Reabold holds a 50.8% equity interest in Danube. Highlights: Site preparations have commenced at the IMIC-2 drill site with drilling on track for Third Quarter 2020; Testing of IMIC-1 now expected to commence in June 2020 due to COVID-19 border closures; 3D seismic acquisition expected to commence in July 2020; Danube is fully funded for testing and appraisal drilling activities and 3D seismic acquisition will be funded by Parta Energy Ltd. Site preparation with local contractors for the IMIC-2 well have already commenced in preparation for future drilling operations planned in Third Quarter 2020. The IMIC-2 well has a planned total depth of 2,200 meters with approximately 23 days to drill and evaluate.