Red 5 Limited reported that it has enjoyed another as-planned month of construction and development progress at its 100%-owned 2.4Moz, 16-year life-of-mine King of the Hills (KOTH) Gold Project in Western Australia for November 2021. The KOTH Project is progressing on schedule for first gold in the June Quarter 2022 and remains within budget, with key construction progress during November 2021 including: On-going installation of the 36-foot diameter SAG mill, with preliminary alignment of the girth gear complete and the two mill pinion gears and mill lubrication skid installed; The process plant control room has been placed into position on the CIL tank platform; The stacker conveyor has been erected as well as the truss sections for conveyors CV01 and CV02; The gyratory crusher's bottom shell, mantle, top shell and ROM bin have been installed; Construction of the ROM wall is nearing completion, with only two lifts remaining; Painting of the exterior of the CIL tanks is complete, with internal coating applied to three of the eight tanks; The stockpile reclaim tunnel is completed and two apron feeders installed; The power station switch room and engine hall are now in place, with two gas engines (3.2MW Jenbacher 620's) and the diesel generators for the plant start-up installed. A further four 4.4MW Jenbacher 624 engines were installed in the engine hall in early December; Fifty power transmission poles for the plant-to-village power corridor have been erected to date; The hot tap into the Goldfields Gas Pipeline has been completed. Installation of the 13km gas lateral pipeline has commenced, with expected completion in early February 2022; and Earthworks for the wall lift on Tailings Storage Facility 4A and 4B are nearing completion.