Red 5 Limited announced that it remains on track for first gold production in the current quarter at its 100%-owned 2.4Moz, 16-year life-of-mine King of the Hills (KOTH) Gold Project, after achieving further key construction and operational readiness milestones during March 2022. Construction and Commissioning: Key construction progress for March included: Commissioning of the crushing circuit has been completed; Commissioning of the gas pipeline has been completed; Commissioning of the power station has been completed to the stage where it is ready to power the process plant; Installation of the solar panels has been completed and wiring is being finalised; and Commissioning of the SAG mill has commenced, with the current critical path to first gold being the commissioning of the Variable Speed Drive. Mining: The company's mining business partner, Macmahon Contractors, recommenced underground mining at King of the Hills on 31 March 2022, in line with the project execution schedule. The start-up underground mine fleet comprises one jumbo, two boggers and a supporting fleet. The initial focus is on mine development, with the first stopes planned to be fired later in the quarter. In the open pit, two fleets are now operating on both day and night shifts as Macmahon ramps up its on-site teams, with a third and final fleet planned to be operational in May 2022.