The order also includes a Premium Service for the maintenance and servicing of the turbines over a period of 15 years
The 50.4 MW wind farm will be built as part of the Pottendijk Energiepark near the village of Nieuw-Weerdinge in the province of Drenthe. In addition to the 14 turbines, the Pottendijk Energiepark will also consist of a solar park with an installed capacity of 50 megawatts. Pottendijk is
The start of supply and construction of the turbines on 84-metre tubular steel towers is scheduled for spring 2022. Commissioning is planned for the end of the same year. With average wind speeds at the site of 6.6 m/s and thanks to the large rotors of the turbines, approx. 130 Gwh of clean electricity generated by wind power alone will be fed annually from the Pottendijk Energiepark into the Dutch grid.
The Group has installed more than 35 GW of wind energy capacity in over 40 markets and in 2020 generated revenues of around