Suite 1800 - Two Bentall Centre

555 Burrard Street

Vancouver, BC V7X 1M9

Tel: (604) 998-4175 Tel: (888) 648-4218

www.sabinagoldsilver.com

December 2, 2020

SBB NR 20-19

SBB - TSX SGSVF - OTCQX

Sabina Gold & Silver Corp. Makes Good Progress on Updated Feasibility Study

Completion Targeted for Q1 2021

Vancouver, BC - Sabina Gold & Silver Corp (SBB.T/SGSVF.OTCQX), ("Sabina" or the "Company") is pleased to report on the status of the Updated Feasibility Study ("UFS") on the proposed Goose

Mine at its 100%-owned Back River Gold Project ("Back River" or the "Project") in Nunavut,

Canada.

"Work continues to advance the updated Back River resource estimate and Goose Project UFS for delivery in Q1, 2021," said Bruce McLeod, President & CEO. "The significant exploration success we have delivered since the September 2015 feasibility study has been incorporated into the resource estimate and mine plan, along with many other improvements to the Project. This work continues to showcase the Goose Mine as a very compelling project: the first of many opportunities on Sabina's 80km long Back River belt. Work continues at site, and we expect to complete our objectives for civil works to enable collaring our exploration decline in the spring of next year. We anticipate mobilizing out of camp in mid December."

UPDATED FEASIBILITY STUDY

Introduction:

The September 2015 feasibility study ("2015 FS") envisioned a 3,000 tonne per day ("TPD") mine producing approximately 200,000 ounces a year over an 11.8-year mine life from a series of three open pits and one underground at the Goose site. Since that time, material discoveries and significant resource extensions have been made at the Project, including the two separate high-grade underground zones at Umwelt. Internal studies were undertaken to determine what potential improvement these areas might have to meaningfully increase the production profile and/or mine life, with a similar or marginally increased throughput, through a combination of open pit and underground mines at the Goose site. The Company is well advanced on the UFS which is expected in early Q1, 2021. The goal for the UFS is to increase gold production on an annual and total life of mine basis, which is expected to improve the overall financial metrics of the Project over the already positive economics demonstrated in the 2015 FS

Resource:

Since the last Back River resource statement was completed, Sabina has drilled over 50,000 meters at the Goose site. This drilling has resulted in several discoveries as well as expansion of the known mineralized horizons at the Project. In 2020, exploration and infill drilling focused on areas that could positively impact the mine plan. Due to COVID, drilling to enable conversion to reserves was not achievable in 2020 for all of the new deposit areas. However, the new resource estimates will include updates to: Umwelt; Goose Main; Echo; and new inferred resources from the Nuvuyak and Llama Extension deposits. The George open pit resources will also be updated to reflect current metal price assumptions.

Reserve, Mining methods and Market Studies:

This Exploration success since the 2015 FS has enabled Sabina to re-envision the mine plan in the UFS. With early access to the high grade V2 Zone located below the Umwelt open pit, Sabina will add high-grade underground feed to the process plant early in the mine life and recover more higher-grade reserves earlier than envisioned in the 2015 FS. The mine plan will incorporate cut and fill mining methods plus cemented rock in select areas of the interface between the open pit and underground deposits, enabling production from areas previously excluded. The mining sequence in the UFS mine plan compared to the 2015 FS is outlined below.

Table 1: UFS re-envisioned mine plan relative to the 2015 Feasibility Study

Mine Production Plan Sequencing

2015 Feasibility Study

2021 UFS

Umwelt Open Pit

Echo Pit

Llama Open Pit

Umwelt Underground

Goose Open Pit

Umwelt Open Pit

Umwelt Underground

Llama Open Pit

Llama Underground

Goose Main Open Pit

Goose Main Underground

Figure 1: Goose Mine Deposits Included in UFS

Processing, Test Work and Recoveries:

Since the 2015 FS, Sabina has undertaken additional metallurgical test work programs which have provided better certainty to the process plant design. These programs included: secondary grinding; leach vs flotation; detox; gravity recovery; and tailings and water quality test work. Results have confirmed the process plant operating parameters as well modest improvements to our baseline recoveries for most deposits. The process plant is designed as a traditional 3,000 TPD, primary/secondary/tertiary crushing, primary/secondary grinding, gravity separation, carbon-in-pulp, leach and detox plant. The plant has a design head grade between 6 and 12gpt with the capability to increase through-put in later years.

Infrastructure:

Sabina has made extensive improvements on all aspects of the Project scope. A brief outline of the significant improvements are as follows:

  • Inaugural winter ice road and sealifts completed, gaining logistical, operational and cost experience which will be incorporated into the UFS;

  • Significant reduction in earthworks for water management structures, (particularly earthworks scheduled for winter construction in the 2015 FS), thus reducing overall Project execution and schedule risk;

  • Larger accommodation complex for an increased work force which enables underground and surface mining operations to run concurrently with construction;

  • Enclosed power plant with larger and fewer power units generating heat recovery providing additional reliability for the power supply during operations;

  • Shorter tailings lines which will reduce operational risk;

  • A Sabina owned, on site oxygen plant and laboratory versus the previous model contemplated; and

  • Three years of on-site seasonal construction experience providing improved understanding of operating in our northern environment which will be applied to estimated costs.

Environmental, Permitting and Social:

The Company is now in receipt of all major authorizations for construction and operations. More recent significant advances in permitting include: the final Project Certificate, received on December 19, 2017; the Type A Water License, received on November 14, 2018; and the listing to enable deposition of tailings on Schedule 2 of the Metals and Diamond Mining Effluent Regulations, received on June 25, 2020. All project modifications were contemplated when the

Company submitted it's 2020 permit modification package to the regulatory authorities. Sabina continues to support the local communities within the region during COVID and continues to receive local support for the project.

CAPEX, OPEX and Financial:

Sabina is maintaining an initial nameplate throughput of 3,000 TPD in the UFS but the study will include an expansion to 4,000 TPD from sustaining capital in years four to five. As per the UFS guidelines, the team is achieving an AACE class III CAPEX estimate with the intention of converting to a class IV estimate for the process plant and selected aspects of remaining project scope after issuing the UFS. This will enable Sabina to obtain a fixed price proposal for construction execution. Completing the UFS while concurrently completing detail engineering will ensure details typically unrealized during a traditional feasibility study will be accurately represented and contribute to the overall accuracy of the study. The CAPEX and OPEX are being built up from first principles to reflect an updated execution strategy of a modified EPCM with Sabina self-managing as the Company has over the last three years. The inclusion of early underground mining activity along with price escalation and inflation, is expected to increase the overall CAPEX and OPEX when compared to the 2015 FS. The impact of an increased gold price and higher recovered ounces on an annual and life of mine basis are expected to improve the project economics when compared to the 2015 FS.

Timeline:

Sacré-Davey Engineering Inc., currently heading detail engineering, will be the overall author with the following companies contributing to the UFS.

This is an excerpt of the original content. To continue reading it, access the original document here.

Attachments

Disclaimer

Sabina Gold & Silver Corp. published this content on 02 December 2020 and is solely responsible for the information contained therein. Distributed by Public, unedited and unaltered, on 02 December 2020 14:10:02 UTC