Sabina Gold & Silver Corp. reported progress on pre-construction activities for its proposed Goose Mine on the 100%-owned Back River Gold Project in Nunavut, Canada. Back River camps continue to work safely under Sabina?s COVID-19 Operational Framework. Testing remains in place upon deployment and once on site, with all employees now required to be fully vaccinated before attending site in order to comply with recently introduced Nunavut regulations. CGT Industrial has provided Sabina with a fixed priced proposal of CAD 130 Million, with an agreed rise and fall mechanism, for materials and consumables for the process plant (crushing circuit, grinding circuit, CIL circuit, pre-leach and tails thickener with tails pumping, gold room, E-houses, control room, O2 plant, fresh water, Truck shop and fire water systems). These components make up approximately 85% of the direct works on site. The proposal is comparable to within 5% of the feasibility study estimate.