The first load-out of four MPs and four TPs for the Rentel wind farm was scheduled for Wednesday 19 July, but the operation was postponed due to the bad weather forecast. The Innovation vessel was eventually loaded on 20 July and departed the same day. Today, on 25 July, Innovation is expected to moor at the deep-sea quay near Sif's premises, where it will be loaded with three MPs and three TPs.

Commissioned by Dredging International, Sif will be manufacturing a total of 42 MPs and in Joint Venture with Smulders 42 TPs for Rentel wind farm.

Sif Holding NV published this content on 25 July 2017 and is solely responsible for the information contained herein.
Distributed by Public, unedited and unaltered, on 27 July 2017 11:58:10 UTC.

Original documenthttps://sif-group.com/en/news/project-updates/438-load-out-of-monopiles-and-transition-pieces-at-rentel-wind-farm

Public permalinkhttp://www.publicnow.com/view/92BD5562C333B04A2131222E4AB5F436F9B9C768