The work on the new Grading Mill in Bollsta is in full swing. There is a lot of activity going on. Reinforcement of the slab i carried out as well as safety procedures for roof safety and installation of the façade.

​​Jimmy Hörnström, project manager for the construction of the adjustment plant, tells more.

'On the whole, the work has gone well so far. The challenge is to adapt to the changes that are constantly taking place in a project of this nature. We have a very large and complex machine plant that is far from standard, which means a lot of coordination at all levels, from machine to construction, and everything in between. The construction progress itself has worked very well. This is despite the fact that King Bore has offered a solid winter in recent months'.

What's happening right now?

'In addition to the ongoing construction work and the fact that we are approaching the end of the design of the construction and property installation, we are entering a new phase where a detailed plan must be made for the machine plant and its testing before the machine assembly can begin. It is a real challenge now in pandemic times to put this puzzle together with the Austrian machine supplier Springer'.

What has been the biggest challen​ge so far?

'To provide all suppliers and contractors with the right information and facts, we need a plan from our machine supplier early in the process. The challenge is to persuade the machine supplier to provide us with that information at an early stage, even before they start manufacturing the machine. We need information about, for example, details around the machine, space requirements, machine access and walkways as it is of great importance for how we design surrounding areas such as dining rooms, toilets, offices and computer rooms etc. Many of these parts have already been determined and the final determination of the machine has a big impact on what the building should look like and where things are placed. The ongoing pandemic has made it difficult to coordinate this'.

What is the next step?

'The plan is for the building to be completed before the start of assembly of the machine plant. It includes the building as such but also all installations that can be completed without being in the way of the machine assembly. We work to convey that image to all parties involved. 'Building ready for assembly' is otherwise a very broad concept and it is important that everyone 'sees' the same thing'.​

Any special milestones that you remem​ber?

'In addition to the decision on the start of Project B700 another memorable milestone was when the procurement of the machine plant was completed. After several years of discussions with four machine suppliers, being able to finally land a contract was very energizing! Another memorable event was when we finally started to build the building for the grading mill. The forthcoming start of the installation of the machine plant in mid-September is a milestone I look forward to'.

Published 3/3/2021

ShareShare on facebookShare on twitterShare on linkedinCopy link

Attachments

  • Original document
  • Permalink

Disclaimer

SCA - Svenska Cellulosa AB published this content on 03 March 2021 and is solely responsible for the information contained therein. Distributed by Public, unedited and unaltered, on 03 March 2021 13:17:00 UTC.