Tietto Minerals Limited provided a project development update for its fully funded 3.35Moz Abujar Gold Project in Côte d'Ivoire, West Africa for November 2021. Tietto is targeting first gold at Abujar in fourth quarter of 2022. Bulk earthworks have been completed for the process plant and camp area.

Construction is progressing well on the administration office, cafeteria building, and the first 120 camp rooms. The civil concrete contractor mobilised to site and has poured blinding concrete for CIL ring beams. Tietto Bulk Earthworks Construction Fleet: Tietto purchased 14 dump trucks and two Hitachi excavators for the bulk earthworks at Abujar, which arrived on site during the month and are in operation.