Tietto Minerals Limited provided a project construction update for its fully funded 3.45Moz Abujar Gold Project in Côte d'Ivoire, West Africa for May 2022. Tietto is on track to deliver first gold at Abujar in Fourth Quarter CY22. Construction is tracking well against schedule, with the first 60 camp rooms occupied.

Blockwork for the administration, clinic and training rooms has been completed. Concreting is advancing, with crusher and ROM bin chamber rafts poured. The first HDPE liners for the tailings storage facility are installed, and construction of the water dam wall has started.

The following figures show a snapshot of the progress achieved on site during April 2022.