The JCU Transaction
UEX will acquire 100% of the shares of JCU from OURD by paying
UEX has committed to retaining JCU as a corporate subsidiary in order for JCU to meet its existing joint venture commitments.
Agreement with Denison Mines Corp.
UEX has signed a binding agreement with Denison Mines Corp. (“Denison”) pursuant to which UEX has agreed to sell 50% of the JCU shares to Denison for a purchase price of
Key terms of the UEX Denison Transaction are as follows:
-Denison has agreed to provide UEX with an interest-free three-month term loan of up to
C$41 million (the “Term Loan”) to facilitate UEX’s purchase of 100% of the shares of JCU.- UEX and Denison have agreed to enter into a shareholders’ agreement governing the management of JCU (the “Shareholders’ Agreement”). UEX will be the manager of JCU as long as Denison does not own more than 50% of the shares of JCU.
- A total of
C$20.5 million of the amount drawn under the Loan will be retired upon UEX transferring 50% of the JCU shares to Denison following the closing of the JCU Transaction.- UEX may extend the Term Loan by an additional three months, in which case interest will be charged at a rate of 4% from the date of the initial advance under the Term Loan until maturity.
- All JCU shares owned by UEX will be held by Denison as security against the Term Loan pursuant to a pledge agreement until the Term Loan is repaid in full. The Term Loan is subject to certain customary terms and conditions and contains standard events of default that protect Denison.
- Should the share purchase agreement be terminated, each of Denison and UEX have agreed to provide the other party with the opportunity to participate on a 50/50 basis in subsequent offers made in relation to an alternative acquisition of JCU.
“The approval of the transaction by OURD Shareholders is a historic day for our Company. UEX shareholders have gained exposure to a strengthened portfolio of top tier uranium development projects that combine growth and production potential in the next cycle. Our assets, combined with our new partnership with Denison, on the JCU projects, will make UEX a unique uranium investment opportunity, possessing a strong and sustainable portfolio of exploration, development and future production opportunities in the
--
Roger Lemaitre , President & CEO,UEX Corporation
Qualified Persons and Data Acquisition
The technical information in this news release has been reviewed and approved by
About UEX
UEX is a Canadian uranium and cobalt exploration and development company involved in an exceptional portfolio of uranium projects, including a number that are 100% owned and operated by UEX, one joint venture with
The Company is also leading the discovery of cobalt in
Our portfolio of projects is located in the eastern, western and northern perimeters of the
About JCU
JCU is a private company that is actively engaged in uranium exploration and development in
JCU has a long history in the Canadian uranium exploration and development sector dating back to 2000, when it acquired a portfolio of Canadian uranium exploration and development assets from
Advisors
FOR FURTHER INFORMATION PLEASE CONTACT:
President & CEO
(306) 979-3849
Forward-Looking Information
This news release contains statements that constitute "forward-looking information" for the purposes of Canadian securities laws. Such statements are based on UEX's current expectations, estimates, forecasts and projections. Such forward-looking information includes statements regarding theCompany’sstrategic plans, completion of the acquisition of JCU, estimates of mineral resources on the Company’s properties and historical estimates of mineral resources on the JCU properties, the outlook for future operations, plans and timing for exploration activities, and other expectations, intentions and plans that are not historical fact. Such forward-looking information is based on certain factors and assumptions, including shareholder approval of the sale of JCU by OURD shareholders, the reliability of historic resource estimates on JCU’s mineral properties and liabilities and working capital of JCU at closing. Important factors that could cause actual results to differ materially from UEX's expectations include uncertainties relating to the historic resource estimates on the JCU properties, continuity and grade of deposits, fluctuations in uranium, cobalt and nickel prices and currency exchange rates, changes in environmental and other laws affecting uranium, cobalt and nickel exploration and mining, and other risks and uncertainties disclosed in UEX's Annual Information Form and other filings with the applicable Canadian securities commissions on SEDAR. Many of these factors are beyond the control of UEX. Consequently, all forward-looking information contained in this news release is qualified by this cautionary statement and there can be no assurance that actual results or developments anticipated by UEX with respect to the acquisition of JCU will be realized. For the reasons set forth above, investors should not place undue reliance on such forward-looking information. Except as required by applicable law, UEX disclaims any intention or obligation to update or revise forward-looking information, whether as a result of new information, future events or otherwise.
Table 1 - JCU ‘s Canadian Exploration Projects and Ownership as of
--------------------------------------------------------------------- |Project |Province |JCU |Partners (%) | | | |Share |* Operator | | | |(%) | | |-------------------------------------------------------------------| |Millennium |Saskatchewan|30.0990|Cameco Corporation* |69.9010| |-------------------------------------------------------------------| |Kiggavik |Nunavut |33.8123|Orano Canada Inc.* |24.0033| | | | |Urangesellschaft Canada|42.1844| | | | |Ltd | | |-------------------------------------------------------------------| |Wheeler River |Saskatchewan|10.0000|Denison Mines Corp.* |90.0000| |-------------------------------------------------------------------| |Christie Lake |Saskatchewan|34.4508|UEX Corporation* |65.5492| |-------------------------------------------------------------------| |Wolly |Saskatchewan|13.1077|Orano Canada Inc.* |64.9997| | | | |Denison Mines Corp. |21.8926| |-------------------------------------------------------------------| |Close Lake |Saskatchewan|10.3128|Orano Canada Inc.* |75.1279| | | | |Cameco Corporation |14.5593| |-------------------------------------------------------------------| |Candle Lake |Saskatchewan|25.0000|Denison Mines Corp.* |44.9400| | | | |Uranium One |30.0600| |-------------------------------------------------------------------| |Beatty River |Saskatchewan|21.4253|Orano Canada Inc.* |56.5303| | | | |UEX Corporation |22.0444| |-------------------------------------------------------------------| |Waterfound |Saskatchewan|26.9830|Orano Canada Inc.* |60.7008| |River | | |Denison Mines Corp. |12.3162| |-------------------------------------------------------------------| |Cree Extension|Saskatchewan|30.0990|Cameco Corporation* |41.9645| | | | |Orano Canada Inc. |27.9365| |-------------------------------------------------------------------| |Moon Lake |Saskatchewan|20.1494|Cameco Corporation* |56.6816| | | | |Orano Canada Inc. |23.1690| |-------------------------------------------------------------------| |Moore Tomblin |Saskatchewan|13.5947|Orano Canada Inc.* |66.6194| | | | |Cameco Corporation |19.7859| ---------------------------------------------------------------------
Table 2 – Historic Indicated and Inferred Resources – JCU Projects
Click Image To View Full Size
(1) Other than the Christie Lake resource estimate, these are historical resource estimates taken from the sources listed below. To the Company’s knowledge, a qualified person has not done sufficient work to classify these historical estimates as current mineral resources. The Company is not treating this information as current mineral resources, has not verified this information and is not relying on it. The Company currently does not plan to conduct any work to verify the historical estimates other than using them to guide its exploratory and possible development work.
(2) The Christie Lake mineral resources were estimated at a cut off of 0.2% U3O8, and are documented in the “Technical Report on the
Christie Lake Uranium Project ,Saskatchewan , Canada” (the “Christie Lake Technical Report”) with an effective date ofDecember 13, 2018 which was filed on SEDAR at www.sedar.com onFebruary 1, 2019 . Inferred resources have been modified from the stated values in the Christie Lake Technical Report to reflect UEX’s increase in the ownership ofChristie Lake Project from 60% to 65.5492% effectiveJanuary 1, 2021 .(3) Certain amounts presented in the Christie Lake Technical Report have been rounded for presentation purposes. This rounding may impact the footing of certain amounts included in the tables above.
(4) Wheeler River resources as reported by Denison’s Prefeasibility Study as posted on
October 30, 2018 on SEDAR.com using a cut-off grade of 0.2% U3O8 for the Gryphon Deposit and 0.8% U3O8 for the Phoenix Deposit. These are treated by the Company as historic resource estimates.(5) Millennium resources as reported by Cameco on their website athttps://www.cameco.com/businesses/uranium-projects/millennium/reserves-resources#measured_and_indicatedas of
December 31, 2020 . Cut-off grades used to estimate resources are unknown. The reader is cautioned that UEX is not aware whether Cameco’s reporting of resources conforms to NI 43-101 and CIM guidelines. These are treated by the Company as historic resource estimates.(6) Kiggavik resources as reported by Orano in their 2019 Activities Report available on their website athttps://www.orano.group/docs/default-source/orano-doc/finance/publications-financieres-et-reglementees/2019/orano_2019_annual_activity_report.pdf?sfvrsn=2abbc744_8and converted from tonnes U to pounds U3O8and from %U to %U3O8. Cut-off grades used to estimate resources are unknown. The reader is cautioned that UEX is not aware whether Orano’s reporting of resources conforms to NI 43-101 and CIM guidelines. These are treated by the Company as historic resource estimates.
(7) UEX ownership of JCU resources listed are based on becoming 50% owner of JCU upon closing of the transaction with OURD on or before
August 3, 2021 .
Table 3 –Indicated and Inferred Resources – Current UEX Projects
Click Image To View Full Size
(1) The mineral resource estimates follow the requirements of National Instrument 43-101 – Standards of Disclosure for Mineral Projects and classifications follow CIM definition standards.
(2)
(3) Certain amounts presented in the Shea Creek Technical Report have been rounded for presentation purposes. This rounding may impact the footing of certain amounts included in the tables above.
(4) The Horseshoe, Raven, and West Bear mineral resources were estimated at a cut off of 0.05% U3O8, and are documented in the “Preliminary Assessment Technical Report on the Horseshoe and Raven Deposits,
(5) Certain amounts presented in the Horseshoe-Raven Technical Report have been rounded for presentation purposes. This rounding may impact the footing of certain amounts included in the tables above.
(6)
(7) Certain amounts presented in the Christie Lake Technical Report have been rounded for presentation purposes. This rounding may impact the footing of certain amounts included in the tables ab
Click Image To View Full Size
Copyright (c) 2021 TheNewswire - All rights reserved.
Copyright (c) 2021 TheNewswire - All rights reserved., source