Background
The Vali gas field, discovered by the joint venture in 2020 is being connected to the
The Vali gas project involves installation of metering facilities at the Vali facility, including separation (located adjacent to Vali-1), installation of flowlines connecting the field's three completed wells to the metering facility, and twin export gas pipelines from the field to tie-in to the Moomba gas gathering network at the Beckler gas field. Installation and pressure testing of the export flowlines was completed successfully in
Update
Site works resumed on
The Vali metering facility is nearing completion, with all equipment now having been installed. Electrical and instrumentation work at Vali-1 is almost complete and progressing well at the metering facility. Mechanical work on the Beckler tie-in point is advancing.
The construction contractor has advised mechanical handover is now expected to occur in early February, following which commissioning will commence immediately.
Vintage commends its contractor team, headed by Global Engineering and Construction (GEC) on remaining injury and environmental incident free over the length of the project to date, particularly given the extreme weather conditions in January.
Odin update
Having completed flowline works for the Vali connection, the crew has commenced trenching for the Accelerated Connection of the Odin gas field as announced
The Accelerated Connection of Odin-1 is being implemented to fast-track supply from the field in advance of a long-term connection. It is anticipated supply from the field, through the Accelerated Connection, can occur in the third quarter of calendar 2023.
*To view tables and figures, please visit:
https://abnnewswire.net/lnk/WCXYFX94
About
Contact:
Managing Director
+61 8 7477 7680
info@vintageenergy.com.au
Copyright (C) 2023 ABN Newswire. All rights reserved., source