We are a diversified holding company with natural gas and electric utility operations (serving customers in Wisconsin, Illinois, Michigan, and Minnesota), an approximately 60% equity ownership interest in American Transmission Company LLC (ATC) (a for-profit electric transmission company regulated by the Federal Energy Regulatory Commission and certain state regulatory commissions), and non-utility energy infrastructure operations through W.E. Power, LLC (which owns generation assets in Wisconsin), Bluewater Natural Gas Holding, LLC (which owns underground natural gas storage facilities in Michigan), and WEC Infrastructure LLC (WECI), which holds ownership interests in several wind generating facilities.

Corporate Strategy

Our goal is to continue to build and sustain long-term value for our shareholders and customers by focusing on the fundamentals of our business: environmental stewardship; reliability; operating efficiency; financial discipline; exceptional customer care; and safety. Our 2021-2025 capital investment plan for efficiency, sustainability and growth, referred to as our ESG Progress Plan, provides a roadmap for us to achieve this goal. It is an aggressive plan to cut emissions, maintain superior reliability, deliver significant savings for customers, and grow our investment in the future of energy.

Throughout our strategic planning process, we take into account important developments, risks and opportunities, including new technologies, customer preferences and commodity prices, energy resiliency efforts, and sustainability. We published the results of a priority sustainability issue assessment in 2020, identifying the issues that are most important to our company and its stakeholders over the short and long terms. Our risk and priority assessments have formed our direction as a company.

Creating a Sustainable Future

Our ESG Progress Plan includes the retirement of older, fossil-fueled generation, to be replaced with zero-carbon-emitting renewables and clean natural gas-fired generation by 2025. When taken together, the retirements and new investments should better balance our supply with our demand, while maintaining reliable, affordable energy for our customers. The retirements will contribute to meeting our goals to reduce carbon dioxide (CO2) emissions from our electric generation.

By the end of 2020, we were able to reduce CO2 emissions from our electric generation fleet by more than 50% below 2005 levels. As a result, we announced new goals in May 2021. We are committing to a 60% reduction in carbon emissions from our electric generation fleet by 2025 and an 80% reduction by the end of 2030, both from a 2005 baseline. We expect to achieve these goals by making operating refinements, retiring less efficient generating units and executing our capital plan. Over the longer term, the target for our generation fleet is net-zero CO2 emissions by 2050.

We have already retired more than 1,800 megawatts (MW) of coal-fired generation since the beginning of 2018, which included the 2019 retirement of the Presque Isle power plant as well as the 2018 retirements of the Pleasant Prairie power plant, the Pulliam power plant, and the jointly-owned Edgewater Unit 4 generating units. As part of our ESG Progress Plan, we expect to retire approximately 1,800 MW of additional fossil-fueled generation by 2025, which includes the planned retirements in 2023-2024 of Oak Creek Power Plant Units 5-8 and the jointly-owned Columbia Units 1-2.

In addition to retiring these older, fossil-fueled plants, we expect to invest approximately $2 billion from 2021-2025 in renewable energy in Wisconsin. Our plan is to replace a portion of the retired capacity by building and owning a combination of clean, natural gas-fired generation and zero-carbon-emitting renewable generation facilities that are anticipated to include the following new investments:



•800 MW of utility-scale solar;
•600 MW of battery storage;
•100 MW of wind;
•100 MW of reciprocating internal combustion engine (RICE) natural gas-fueled
generation; and
06/30/2021 Form 10-Q     43      WEC Energy Group, Inc.


--------------------------------------------------------------------------------

Tab le of Contents •the planned purchase of 200 MW of capacity in the West Riverside Energy Center - a new, combined-cycle natural gas plant recently completed by Alliant Energy in Wisconsin.

For more details, see Liquidity and Capital Resources - Capital Resources and Requirements - Capital Requirements - Significant Capital Projects.

In addition, we previously received approval from the Public Service Commission of Wisconsin (PSCW) to invest in 300 MW of utility-scale solar within our Wisconsin segment. Wisconsin Public Service Corporation (WPS) has partnered with an unaffiliated utility to construct two solar projects in Wisconsin: Two Creeks Solar Park (Two Creeks), now in service, and Badger Hollow Solar Park I (Badger Hollow I), expected to enter commercial operation in the fourth quarter of 2021. WPS owns 100 MW of Two Creeks and will own 100 MW of Badger Hollow I for a total of 200 MW. Wisconsin Electric Power Company (WE) has partnered with an unaffiliated utility to construct Badger Hollow Solar Park II that is expected to enter commercial operation in December 2022. Once constructed, WE will own 100 MW of this project.

In December 2018, WE received approval from the PSCW for two renewable energy pilot programs. The Solar Now pilot is expected to add 35 MW of solar generation to WE's portfolio, allowing non-profit and governmental entities, as well as commercial and industrial customers to site utility owned solar arrays on their property. Under this program, WE has energized 18 Solar Now projects and currently has another four under construction, together totaling more than 24 MW. The second program, the Dedicated Renewable Energy Resource pilot, would allow large commercial and industrial customers to access renewable resources that WE would operate, adding up to 150 MW of renewables to WE's portfolio, and helping these larger customers meet their sustainability and renewable energy goals.

We also continue to reduce methane emissions by improving our natural gas distribution system. Our initial 2030 goal called for a 30% reduction in methane emissions from a 2011 baseline. Given advancements with renewable natural gas, we are setting a new target across our natural gas distribution operations to achieve net-zero methane emissions by the end of 2030.

Reliability

We have made significant reliability-related investments in recent years, and in accordance with our ESG Progress Plan, expect to continue strengthening and modernizing our generation fleet and distribution networks to further improve reliability.

Below are a few examples of reliability projects that are proposed or currently underway.

•WE is constructing approximately 46 miles of natural gas transmission main to increase the quantity and reliability of natural gas service in southeastern Wisconsin. This project, called the Lakeshore Lateral Project, is expected to be completed by the end of 2021.

•WE and Wisconsin Gas LLC (WG) each plan to construct their own liquefied natural gas (LNG) facilities to meet anticipated peak demand. Subject to PSCW approval, commercial operation of the LNG facilities is targeted for the end of 2023.

•The Peoples Gas Light and Coke Company continues to work on its Natural Gas System Modernization Program, which primarily involves replacing old iron pipes and facilities in Chicago's natural gas delivery system with modern polyethylene pipes to reinforce the long-term safety and reliability of the system.

•WPS is in the final year of its System Modernization and Reliability Project, which involves modernizing parts of its electric distribution system, including burying or upgrading lines. WE, WPS, and WG also continue to upgrade their electric and natural gas distribution systems to enhance reliability.

For more details, see Liquidity and Capital Resources - Capital Resources and Requirements - Capital Requirements - Significant Capital Projects.

Operating Efficiency

We continually look for ways to optimize the operating efficiency of our company and will continue to do so under the ESG Progress Plan. For example, we are making progress on our Advanced Metering Infrastructure program, replacing aging meter-reading equipment on both our network and customer property. An integrated system of smart meters, communication networks, and data 06/30/2021 Form 10-Q 44 WEC Energy Group, Inc.

--------------------------------------------------------------------------------

Tab le of Contents management programs enables two-way communication between our utilities and our customers. This program reduces the manual effort for disconnects and reconnects and enhances outage management capabilities.

We continue to focus on integrating the resources of all our businesses and finding the best and most efficient processes while meeting all applicable legal and regulatory requirements.

Financial Discipline

A strong adherence to financial discipline is essential to meeting our earnings projections and maintaining a strong balance sheet, stable cash flows, a growing dividend, and quality credit ratings.

We follow an asset management strategy that focuses on investing in and acquiring assets consistent with our strategic plans, as well as disposing of assets, including property, plants, equipment, and entire business units, that are no longer strategic to operations, are not performing as intended, or have an unacceptable risk profile.

Our investment focus remains in our regulated utility and non-utility energy infrastructure businesses, as well as our investment in ATC. In our non-utility energy infrastructure segment, we have acquired or agreed to acquire majority interests in eight wind parks, capable of providing more than 1,550 MW of carbon-free energy in total. These renewable energy assets represent more than $2.3 billion in committed investments and have long-term agreements to serve customers outside our traditional service areas. Production tax credits from these wind investments reduce our cash tax expense. See Note 2, Acquisitions, for additional information on recent transactions.

We expect total capital expenditures for our regulated utility and non-utility energy infrastructure businesses to be approximately $15.0 billion from 2021 to 2025. In addition, we currently forecast that our share of ATC's projected capital expenditures over the next five years will be $1.1 billion. Specific projects included in the $16.1 billion ESG Progress Plan are discussed in more detail below under Liquidity and Capital Resources - Capital Resources and Requirements - Capital Requirements - Significant Capital Projects.

Exceptional Customer Care

Our approach is driven by an intense focus on delivering exceptional customer care every day. We strive to provide the best value for our customers by demonstrating personal responsibility for results, leveraging our capabilities and expertise, and using creative solutions to meet or exceed our customers' expectations.

A multiyear effort is driving a standardized, seamless approach to digital customer service across our companies. We have moved all utilities to a common platform for all customer-facing self-service options. Using common systems and processes reduces costs, provides greater flexibility and enhances the consistent delivery of exceptional service to customers.

Safety

Safety is one of our core values and a critical component of our culture. We are committed to keeping our employees and the public safe through a comprehensive corporate safety program that focuses on employee engagement and elimination of at-risk behaviors.

Under our "Target Zero" mission, we have an ultimate goal of zero incidents, accidents, and injuries. Management and union leadership work together to reinforce the Target Zero culture. We set annual goals for safety results as well as measurable leading indicators, in order to raise awareness of at-risk behaviors and situations and guide injury-prevention activities. All employees are encouraged to report unsafe conditions or incidents that could have led to an injury. Injuries and tasks with high levels of risk are assessed, and findings and best practices are shared across our companies.

Our corporate safety program provides a forum for addressing employee concerns, training employees and contractors on current safety standards, and recognizing those who demonstrate a safety focus.