- Power Plants
The project is progressing in line with international ESG standards, high quality and occupational safety policies. To date, 591,105 m3 of excavation and 104,390 m3 of backfill have been completed. A progress rate of 80% has been achieved in foundation pile works and 6.9% of concrete casting works have been completed. In addition, 14.6% of procurement packages has been committed and an overall progress rate of 7.41% has reached in the project.