Harmarm Energy Income Trust plc announced that its 11 MW /22 MWh Broadditch project (located in Kent), has now been successfully energized and is expected to be operational before the end of March 2023. This is the Company's second project to be energised and takes the total operational capacity within the Company's portfolio to 109 MW /218 MWh. The project was developed by Harmony Energy Limited and construction of the project was managed by Tesla with oversight from the Harmony Energy Project Team.

The project will be operated through Autobidder, Tesla's algorithmic trading platform, which has also been deployed at the Company's Pillswood project and has demonstrated a strong track record over the past two years in operating the Holes Bay and Contego projects - two existing battery storage projects also developed by Harmony Energy Limited (with FRV).