This document has been translated from the Japanese original of " Shimane Genshiryoku Hatsudensho 2gouki ni okeru Shiyoumae Kakunin Shinseisho no Henko ni tsuite " for reference purposes only.

In the event of any discrepancy between this translated document and the Japanese original, the original shall prevail.

April 30, 2024

Name of Listed Company: THE CHUGOKU ELECTRIC POWER CO., INC.

Code:

9504Prime of Tokyo Stock Exchange

Representative:

Nakagawa Kengo, Representative Director President & Chief Executive Officer

Contact:

Kishira Makoto, Manager, Nuclear Power Administration Group, Power

Generation Division

TEL:

+81-82-544-2639

Notice on Revision of Application for Pre-operational Confirmation of

Shimane Nuclear Power Station Unit 2

1. Outline of Revision

On September 11, 2023, we have submitted an application for pre-operational confirmation, including a process of an operator's pre-operational inspections, to the Nuclear Regulation Authority (NRA) for the restart of commercial operation of Shimane Unit 2. (This matter was disclosed in "Notice on Submission of Application for Pre-operational Confirmation of Shimane Nuclear Power Station Unit 2," dated September 11, 2023.)

The safety construction work currently underway is expected to be prolonged due to congestion with the facility inspections*1 in preparation for the restart and thus we decide to revise the completion date from May 2024 to October 2024 as well as the process of an operator's pre-operational inspections*2. Accordingly, we have revised the content of the application for pre-operational confirmation and submitted to the NRA on April 30, 2024.

*1 Considering the extended shutdown period of Shimane Unit 2, inspections of each facility and equipment are being conducted in preparation for restarting operations.

*2 In the process of the revised operator's pre-operational inspections, the processes related to the restart are scheduled as follows.

(Previous)

(Revision)

Start of fuel loading

June 2024

October 2024

Reactor start-up

August 2024

December 2024

Generator paralleling (restart)

August 2024

December 2024

Resumption of commercial operation

September 2024

January 2025

2. Impact on Financial Results

We have announced the forecasts of financial result for the year ending March 31, 2025 on April 30, 2024 with the consideration of the revision in process resulting in an increase of material costs due to a decrease in nuclear capacity factor.

We will continue to take all possible measures to ensure the safety construction work as well as to respond appropriately to the pre-operational confirmation conducted by the NRA, with the aim to create the power station that provides peace of mind to everyone in the local community.

Attachment: Revision of Application for Pre-operational Confirmation of Shimane Nuclear Power Station Unit 2

Revision of Application for Pre-operational Confirmation

Attachment

of Shimane Nuclear Power Station Unit 2

At Shimane Unit 2, the construction of various safety measure facilities based on the new regulatory requirements is underway, including new installation and modification work, in accordance with the construction plan approved on August 30, 2023.

Before these facilities can be put into use, they must undergo operator's pre-operational inspections*1 by Chugoku Electric Power and a pre-operational confirmation*2, which should be conducted during inspection periods (1) to (3) shown below, by the Nuclear Regulation Authority (NRA).

*1 The inspections are carried out by the operator to check that the construction work is proceeding in accordance with the approved contents (materials, dimensions, functions, performance, etc.) of the construction plan.

Some of the operator's pre-operational inspections for Shimane Unit 2 that can be conducted prior to the approval of the construction plan have been started in advance since March 2023.

*2 The confirmation is conducted by the NRA to check that the operator's pre-operational inspections are conducted properly and completed. This is done by witnessing the operator's inspections and by confirming records.

In this application for pre-operational confirmation, we revised the process of operator's pre- operational inspections as follows.

[Main Process of the Operator's Pre-operational Inspections at Shimane Unit 2 (Revision details)]

Postponed periods

2023

2024

2025

9

10

11

12

1

2

3

4

5

6

7

8

9

10

11

12

1

2

3

- (1) Fuel is loaded into the reactor after

pre-operational

Safety measure construction period

confirmation of the inspections is

completed.

- (2) After completion of pre-operational

confirmation of

the inspections, the reactor start-up operation is

performed, and then the generator is paralleled

(power generation is resumed).

(1) Inspections before loading fuel

- (3) Upon completion of pre-operational confirmation of

the inspections, the NRA will issue a pre-

operational confirmation certificate and the plant

will resume commercial operation.

(2) Inspections before reactor start-up

(3) Inspections before resumption of commercial operation

The processes of operator's pre-operational inspections pertaining to restart are scheduled as follows.

Start of fuel loading: October 2024, Reactor start-up: December 2024, Generator paralleling (restart): December 2024, Resumption of commercial

operation: January 2025.