To accurately gauge the scale of this cycle, an AI data center should be viewed as an integrated electrical and thermal system built around extremely dense servers. AI accelerators, notably GPUs and ASICs, generate significant heat, consume vast amounts of electricity, and must be connected to liquid cooling systems, high-speed cabling, transformers, switchgear, and backup power devices. Goldman Sachs highlights that next-generation AI data centers often cost between $15m and $20m per megawatt, compared to roughly $10m per megawatt for more traditional facilities.
The most telling example is that of an hyperscaler that may have already secured its chips, signed its construction contracts, and ordered its servers, yet remains waiting for the electrical equipment necessary to commission the site. In such cases, capital is committed and expenditures appear on the balance sheet, but the computing capacity is not yet generating revenue. McKinsey reports that lead times in North America can reach 80 weeks for certain medium-voltage switchgear and 50 weeks for transformers, making power a primary bottleneck in the deployment of AI capacity.
This constraint is also shifting the market's interpretation of the theme, as potential winners are no longer found solely in semiconductors or major cloud providers. Industrial players capable of rapidly delivering reliable, tested electrical, thermal, and mechanical systems compatible with future chip architectures are positioned to capture a significant share of data center infrastructure spending. McKinsey further notes that hyperscalers are increasingly prioritizing suppliers able to align early with the roadmaps of GPU manufacturers and proprietary chip designers.
According to reports from Goldman Sachs and McKinsey, the next phase of the cycle should therefore be monitored through very tangible indicators: 1) lead times for transformers, 2) the adoption of liquid cooling as rack density increases, 3) the cost per megawatt of new data centers, 4) the actual utilization rate of chips, and 5) the ability of industrial suppliers to remain synchronized with the technical roadmaps of hyperscalers and semiconductor manufacturers.
Goldman Sachs and McKinsey bring the AI boom back to its physical constraints
As tech giants ramp up their AI spending announcements, Goldman Sachs reminds investors that the challenge extends far beyond purchasing more chips or building new servers. In its baseline scenario, the bank estimates that AI infrastructure could require approximately $765bn in spending by 2026, rising to $1,600bn by 2031, representing nearly $7,600bn in cumulative investment between 2026 and 2031 across computing, data centers and energy.
Published on 05/07/2026 at 04:44 pm EDT




















