BCPL Railway Infrastructure Limited updated its esteemed stakeholders that the Company has received an Electrification project under Gati Shakti Sealdah Division of Eastern Railway. This order has been received for the work of 25 KV OHE and allied electrical works in connection with Provision of 12 Mtrs. Wide FOB at i) KNJ Stn., ii) STB Stn., iii) BPC Stn., iv) BTY Stn.

and v) BNJ Stn. of Sealdah Division. The total project cost comprises of INR 32.62 million and it is expected to be executed over a period of 12 months.