Gatos Silver announced that the company expects plant throughput in 2024 to average in the top half of previously announced guidance range of 3,000 and 3,300 tonnes processed per day. This compares to 2,935 tonnes per day in 2023. The LGJV continues to strive to achieve sustainably higher plant throughput rates as mine debottlenecking efforts continue with a medium-term target to sustain 3,500 tonnes per day beyond 2024, or 40% above original design capacity.