The TAIF Business Centre project of ENKA in the city of Kazan in Tatarstan of the Russian Federation was 95.6% complete as of the end of 2020. A total of 5,540,057 person-hours were expended without LTI during the course of the project.

Progress on the architectural works amounted to 96%. In this context, 17,595 m2 of the brick walls and 15,443 m2 of the gypsum board partition walls had been erected, and a total of 33,750 m2 of screed had been poured. In addition, 25,160 m2 of ceramic floor covering and 3,179 m2 of natural stone floor covering works, 2,101 m2 installation of glass partitions, 5,523 m2 of application of ceramic, 2,432 m2 of granite and marble wall coverings had been carried out. The rates of progress on the mechanical works were roughly 99% and about 97% for the electrical works. The rate of progress on the weak current systems had reached only 69% due to revisions made by the employer.

For more information about the project please visit: https://www.enka.com/portfolio-item/taif-business-center-2/

Attachments

  • Original document
  • Permalink

Disclaimer

Enka Insaat ve Sanayi AS published this content on 05 January 2021 and is solely responsible for the information contained therein. Distributed by Public, unedited and unaltered, on 05 January 2021 14:07:09 UTC