Pure Gold Mining Inc. provided an update on recent production milestones achieved and upgrades completed in the month of August at the Company's high-grade PureGold Mine in Red Lake, Ontario. Highlights from the month of August include: Completed installation of all six CIP interstage screens and a trommel screen on the SAG mill in August, leading to a new single day record of 1,037 tonnes of ore1 on August 31, 30% higher than the current design capacity of 800 tpd; Mined high-grade stopes from both Main Ramp and the East Ramp areas for the first full calendar month in August leading to a new single day production record of 2,050 tonnes of ore brought to surface on August 17; Achieved average daily ore throughput of 703 tpd for the month of August inclusive of planned downtime to install interstage and trommel screens; Achieved average daily ore throughput of 870 tpd for the last week of August; Mined average stope grade of 6.5 g/t Au for the month of August; Processed average total mill feed grade of 5.6 g/t Au for the month of August; Poured 5,535 ounces of gold during the month of August, a new monthly record; Completed commissioning of the water treatment plant; and Achieved Main Ramp average daily advance rate of 5.6 metres/day.