Salt Lake Potash Limited provided an update on its Lake Way Project at Wiluna in Western Australia. The Project remains on schedule to deliver first SOP production in the March quarter of 2021. Total project is now 60% complete on an earned value basis. Major vendor procurement packages over 90% commited with fixed costs. At the process plant site concrete foundations poured by Flanco are more than 80% complete, installation of structural steel supplied by Metro Steel has commenced and first carbon steel tanks have been installed by Proweld. Long lead procurement items have commenced arriving on site including the Veolia crystallisers with associated components and tanks, and transformers from Wilson. Vendor packages currently in transit to site include lump breaker, attritioners, wet screens and centrifuges. All permanent buildings are now on site and installed including the permanent village, construction village, warehouse, workshop, administration, reagents, laboratory, ablutions, crib rooms and 4G communications has been installed across site. Development of On Lake infrastructure continues to progress. Work has commenced on the fourth of six pond trains and 62km of trenches have now been completed. The Paleochannel drilling programme continues with the sixth bore hole now underway. All bores have intercepted basal sands in line with the model prediction.