O U R M I N I N G I M P R OV E S L I V E S | |
JSE: SSW | NYSE: SBSW |
LEVEL 3 ENVIRONMENTAL INCIDENTS IN 2020
No level 4 or 5 environmental incidents occurred during 2020.
No | Incident date | Incident level Operation/site | Description | Remedial action taken | Current status |
SA PGM operations
1 | 24 April 2020 | 3 | Kroondal - K150 | Excessive rainfall of some 100mm between 1 and 21 April 2020 |
return water | caused an uncontrolled decant from the K150 return water dam. | |||
dam | This incident was exacerbated by plant-related stoppages due to | |||
COVID-19. |
No negative environmental consequences were observed.
• Plant operations were resumed to reduce water flow to the return Incident closed on 11 June 2020 water dam via the tailings storage facilities
- The return water dam was desilted and reeds were removed to increase storage capacity
2 | 24 April 2020 | 3 | Rustenburg | An excessive rainfall event that occurred between |
- UG2 | 1 and 21 April 2020 caused an uncontrolled decant of some | |||
concentrator | 30,000kl from the Klipgat return water dam. This incident was | |||
exacerbated by plant-related stoppages due to COVID-19. |
No negative environmental consequences were observed.
- Plant operations were resumed to reduce water to the return water dam via the tailings storage facilities
- The return water dam to be desilted and reeds were removed to increase storage capacity
Desilting and reed removal to be completed by mid-2021
SA gold operations
3 | 3 July 2020 | 3 | Kloof | Failure of the Leeudoorn tailings storage facility slurry pipeline | • The spilled tailings was contained and cleaned up | The incident was closed on |
due to the substandard welding of the pipe at the flange. Some | • Improved quality checks on the pipelines | 21 October 2020 | ||||
1,179m3 of tailings spilt via a stormwater canal to the Loopspruit | • Increased security patrols on the pipeline route | |||||
causing some tailings material to enter the water course. It was, | ||||||
however, a short-term spill lasting two hours. | ||||||
No negative environmental impacts were observed. | ||||||
4 | 3 September 2020 | 3 | Rand Uranium | Sabotage of the Cooke Plant slurry pipeline by illegal miners caused | • Clearance of the spillage on the road | The incident was closed on |
surface operation | Dump 20 to fail. The failure resulted in some 1,159m3 of tailings | • Containment of spilt slurry into the soil with | 25 September 2020 | |||
spilling next to the pipeline and onto a road. However, no tailings | constructed berms | |||||
material entered the water course. | ||||||
• Cleaning of contained slurry when dried | ||||||
It was a short-term spill of a few hours. No negative environmental | • Increase of security patrols on the pipeline route | |||||
impact was observed. | ||||||
No | Incident date | Incident level | Operation/site | Description |
US PGM operations | ||||
5 | 23 November 2020 | 3 | Stillwater | High winds resulted in wind-blown tailings that exceeded air permit |
standard of 20% opacity at Hertzler tailings facility. This was a self- | ||||
reported violation to Air Quality Bureau. |
Remedial action taken | Current status |
• Additional mine water was added in an effort to submerse | Closed - 30 November 2020 |
tailings, as an interim measure |
- Magnesium chloride solution was applied as dust suppressant to exposed tailings
- Weekly opacity readings conducted to show corrective action effectiveness
- Ongoing weekly monitoring to monitor the need for additional magnesium chloride application
PAGE1 1
O U R M I N I N G I M P R OV E S L I V E S | |
JSE: SSW | NYSE: SBSW |
LEVEL 3 ENVIRONMENTAL INCIDENTS IN 2020 CONTINUED
An update on the 2019 level 3 incidents reported that were not closed during the previous reporting period:
Date | Place | Description and remedial action |
SA PGM operations | ||
13 November 2019 | Marikana | On 13 November 2019 the Rowland corner dam discharged into a tributary of the Klein Blesbokspruit for some 36 hours. |
This unplanned discharge incident impacted clean surface water and ground water. The incident was reported to the relevant | ||
regulatory authority. |
Subsequent detailed root cause analysis identified the inadequate flexibility to transfer the water to other operations as the main deficiency.
Actions taken included stopping the plant feeding the Rowland corner dam to reduce the water volumes to the corner dam.
Progress/Status update
- Additional mine water was added in an effort to submerse tailings, as an interim measure
- Magnesium chloride solution was applied as dust suppressant to exposed tailings
- Weekly capacity readings conducted to show corrective action effectiveness
- Ongoing weekly monitoring to monitor the need for additional magnesium chloride application
11 December 2019 Rustenburg During an environmental inspection, Naude dam at Thembelani 1 shaft was found overflowing into the natural environment. The overflow occurred for approximately three days, and the volume was estimated to be some 5,000m3. Water samples for water quality analysis were taken.
Subsequent detailed root cause analysis identified deficiencies:
- Heavy rainfall
- Accumulation of upstream flows (first flush)
- Klipfontein diversion was not closed
- Dam wall at the Naude dam is damaged
Actions:
- Proceed with the Section 21(c) and river crossing stabilisation project
- Identify and implement proper measures to ensure the effective operation of the Klipfonteinspruit diversion around the Naudé Dam
- Remove litter from the watercourse
Sibanye-Stillwater plans to implement adequate measures to effectively divert the Klipfonteinspruit around the Naudé dam after all authorisations are in place. Due to the time it could take to obtain the necessary authorisations, the Department of Water and Sanitation (DWS) should be requested to give a 'directive' to implement measures in the interim, awaiting the authorisations.
A process to repair the Naude dam is underway
For more information on our actions to minimise our environmental impact, please refer to the full 2020 Integrated report available at https://www.sibanyestillwater.com/news-investors/reports/annual.
OUR VISION: Superior value creation for all our stakeholders through the responsible mining of our mineral resources
FOR MORE INFORMATION, CONTACT:
James Wellsted | Email: | ir@sibanyestillwater.com |
Senior Vice President: Investor Relations | Website: www.sibanyestillwater.com |
2
Attachments
- Original document
- Permalink
Disclaimer
Sibanye Stillwater Limited published this content on 22 April 2021 and is solely responsible for the information contained therein. Distributed by Public, unedited and unaltered, on 22 April 2021 08:07:06 UTC.