Tigers Realm Coal (ASX: TIG)

ASX Release - December 2021 Quarterly Report

For personal use only

December 2021 Quarterly

ASX RELEASE

Production and Activities Report

25 January 2022

December 2021 Quarter Operational Activity

(Previous)

Quarter

Year to

2021

Ended

date

Annual

Guidance

Dec-21

Dec-21

ROM coal mined

kt

303

1 025

950-1 000

Coal delivered to Beringovsky Port

kt

249

926

Coal loaded

kt

155

885

Coal sold

kt

197

911*

800-850

Total coal stocks

kt

567

567

Waste mined

bcm

1 021

4 063

ROM strip ratio

bcm : t

3.4:1

4.0:1

*Including coal sold ex-stockpile to local customers and coal loaded in the prior quarter

Highlights

  • Safety - The cumulative Total Reportable Injury Frequency Rate ("TRIFR") increased to 2.58 per million hours from 2.35 in the September quarter due to 1 LTI in December quarter. Roughly 70% of TIG personnel have been vaccinated against COVID-19 with the Sputnik V vaccine.
  • Coal Production - 303kt of coal was mined during the December quarter, 1 025kt mined during 2021, an increase of 29% compared to 2020.
  • Port operations - During Q4 2021 TIG has loaded 155kt, achieving 885kt loading in 2021, an increase of 16% compared to 2020 and the maximum annual volume achieved in the port's history. The average loading rate in 2021 increased to 8.2kt per weather working day ("pwwd") compared to 6.5kt pwwd in 2020.
  • CHPP Project - The CHPP equipment is fully installed, and winterization of the plant is near completion. TIG expects to complete commissioning procedures and begin processing washed coal during the March quarter 2022.
  • Sales - In 2021 TIG sold 911kt, an increase of 18% compared to 2020 results. Overall, 15 vessels were shipped, two of them with metallurgical coal.
  • Compliance and licencing - The Company is in compliance with all material license obligations.
  • NED Appointment - Mitch Jakeman appointed to TIG Board on 17 January 2022.

Page 1 of 8

Tigers Realm Coal (ASX: TIG)

ASX Release - December 2021 Quarterly Report

Health and Safety

The vaccination program at site using the Sputnik V vaccine is ongoing. More than 70% of staff members are vaccinated. Measures taken during 2021 allowed TIG to avoid any negative impact of COVID on our operations.

only

TIG's cumulative TRIFR increased to 2.58 per million hours worked, from 2.35 in the September 2021

quarter due to 1 lost time injury ("LTI") recorded in the December quarter. The Company continues

to improve and support its workplace safety culture with training, communication and integration of

success in this area into management's compensation structure.

Mining and Haulage Operations

use

October

November

December

Total

ROM coal mined

kt

91

119

93

303

Coal delivered to Beringovsky Port

kt

91

86

72

249

Waste mined

kbcm

344

400

277

1 021

Stripping ratio

bcm : t

3.8

3.4

3.0

3.4

Total Coal stocks (end of month)

kt

492

478

567

During the December quarter, TIG mined 303kt of ROM coal and delivered 249kt to the port. Overall,

during 2021 TIG mined 1 025kt of ROM coal which is 29% higher than in 2020. The quarterly average

stripping ratio decreased from 3.5:1 in the September quarter to 3.4:1 in the December quarter.

Average annual stripping ratio for 2021 amounted to 4.0:1, a significant decrease from the 5.3:1 of

2020 which was due to focussing our mining activities on Seam 3, which material will be sent for

further processing with CHPP in 1H 2022. Coal haulage to port increased to 926kt, a 47% increase

over 2020. Maximum truck haulage per day reached 5kt.

Beringovsky Port Operations

personal

October

November

December

Total

Coal loaded

kt

95

60

-

155

Coal sold

kt

60

133

4

197

(Coal loaded usually differs from coal sold for two reasons. First, coal may be loaded in a previous period but recognized as sold upon

completion of loading. Second, some relatively small amounts of coal were sold ex-stockpile to local customers.)

For

Page 2 of 8

Tigers Realm Coal (ASX: TIG)

ASX Release - December 2021 Quarterly Report

For personal use only

During 2021 TIG's loading rate increased to 8.2kt per weather working day ("pwwd") compared to 6.5kt pwwd in 2020. As TIG's port has a limited navigational season with weather conditions, particularly toward the end of the season, which can be unpredictable, it is critical to maximize loading when weather allows. Multiple factors impact average loading rates, among these are effective scheduling of bulker arrivals, pre-season & intra-season dredging so that barges are able to work with maximum loads and proper planning of inter-season maintenance.

The building of 5th 500t barge is in progress and TIG expects to receive the barge on site by the start of the 2022 shipping season. This additional barge will further increase TIG's annual loading capacity and it has also been configured with a front-access ramp to enable better handling of incoming equipment and spares than the currently utilized 100t barges.

Page 3 of 8

Tigers Realm Coal (ASX: TIG)

ASX Release - December 2021 Quarterly Report

Coal Handling and Process Plant (CHPP) Project

For personal use only

Construction works continued to be adversely affected by extremely poor weather conditions, especially during December. Nonetheless, the CHPP equipment is now fully installed, and the plant cladding and winterization is close to being complete. TIG expects to complete testing and commissioning procedures and begin running at nominal capacity in the March quarter. During this period, we will also complete installation of key CHPP-related infrastructure such as the boiler facility.

Coal Sales and Marketing

During October - November, TIG completed loading three export cargos for a total of 131kt and two domestic cargos totaling 10kt.

One of these cargos was an export semi-soft coking coal cargo. All the others were thermal coal cargos.

Total sales for the year 2021 were 911kt, (120kt SSCC, remainder thermal) slightly ahead of our total sales volume guidance range.

Market Outlook

In general, the global coal market undertook a downward correction in October 2021, as a result of the introduction of a Chinese Government price cap, and a directive given to Chinese producers to increase coal production. In addition, Chinese steel demand fell heavily through October to December, on the back of a significant downturn in the Chinese construction sector.

Coking Coal

The Asian coking coal market changed significantly in the December quarter, driven by restricted supply from Australia and strong demand from India and North East Asia. China, which had been a strong market for most of the year, was significantly impacted by a downturn in the residential construction market in China. The impact on steel demand has been material, with coke makers operating at less than 50% of capacity.

The result of the change (negative in China, positive outside of China) is that the spot coking coal market has adjusted, and CFR China prices for hard coking coal (HCC) are now slightly lower than Australian FOB prices.

Page 4 of 8

Tigers Realm Coal (ASX: TIG)

ASX Release - December 2021 Quarterly Report

Thermal Coal

The Asia-Pacific thermal coal market corrected strongly on the back of the Chinese government price

cap introduced in late October. The price of 5500 kcal NAR domestic thermal coal at Qinhuangdao

dropped by roughly a third. This led to an even sharper price correction for imported coal with many

cargoes being rejected. By late December Russian and Indonesian prices were about 40% lower than

in early October.

In late December, the Indonesian government announced a ban on exports that has continued into

mid-January. As a result, Newcastle 6,000 NAR and 5,500 NAR coals have recovered. This recovery is

onlylikely to be temporary. No such recovery has been observed in the Russian high-ash price index with

use

current spot market prices lower than in December.

NED Appointment

On 17 January 2022 Tigers Realm Coal appointed Mr. Mitch Jakeman as a non - executive Director to

the Board. Mitch is a well credentialed and highly experienced mining executive having held senior

operational and management roles with various mining companies including Shell Coal Australia,

personal

Anglo Coal Australia and Stanmore Coal.

In Q4 2021 TIG continued its work in the following areas:

We look forward to working with Mitch as we continue to develop and grow the Company.

Capital investments

New capital investments during the December quarter included:

Diesel generator for CHPP

Continuing construction of CHPP building

Continuing construction of road culverts

Water runoff management infrastructure completed

General repair and maintenance projects in the port

Stakeholder relations

For

Environment

Plans for water protection and water management measures for 2022 for the discharge of

wastewater were developed and agreed upon

Water runoff management infrastructure was completed in the port (as noted above)

The adverse weather action plan was updated and agreed with

An article was prepared for the Far North newspaper describing the environmental protection measures taken in 2021 (https://www.ks87.ru/ehkonomika/169/13662)

Government and community relations

  • TIG was included in the list of key projects of the Russian Federation under the personal control of the supervising Deputy Prime Minister of the Russian Federation

Page 5 of 8

This is an excerpt of the original content. To continue reading it, access the original document here.

Attachments

  • Original Link
  • Original Document
  • Permalink

Disclaimer

Tigers Realm Coal Limited published this content on 24 January 2022 and is solely responsible for the information contained therein. Distributed by Public, unedited and unaltered, on 24 January 2022 21:45:04 UTC.