We have applied separately in three divisions for approval of construction planning regarding Specific Safety Facilities (SSFs) of Sendai nuclear power station unit No.2.
Today, we received the approval regarding 'Facilities installed in a reactor subsidiary building' which is the first division, from Nuclear Regulatory Authority (NRA).

 We will continue to make an effort to deal with the NRA's inspections respectfully and sincerely, for improving safety and reliability of nuclear power stations.

(Reference)

 Applications for approval of construction planning were submitted separately as below with a view to install SSFs within the time required by laws.

1. Facilities installed in a reactor subsidiary building
2. Newly installed buildings
3. Newly installed facilities

○Status of application regarding SSFs of Sendai nuclear power station unit No.2

Facilities installed in a reactor subsidiary building (Application)
July 10, 2017
(Revision)
May 17, 2018
(Approval)
 August 10, 2018 (Today)
Newly installed buildings (Application)
August 8, 2017
(Revision)
April 26, 2018
May 28, 2018
June 6, 2018
Newly installed facilities (Application)
March 9, 2018