With national energy supplies a critical focus, the Australian Energy Market Operator (AEMO) is calling for prioritised investment in new transmission lines to ensure the electricity supply is secure.

More than $12 billion of investment has been highlighted as a top priority for federal and state government approval and progression. AEMO's Integrated System Plan (ISP), a 30-year roadmap identified critical projects requiring funding to support the supply of reliable and affordable energy, while reaching net zero by 2050.

One of the critical projects identified is the Marinus Link and North West Transmission Developments project, a 1500 megawatt capacity undersea and underground electricity and telecommunications connection linking North West Tasmania to the Latrobe Valley in Victoria. With Tasmania home to some of Australia's most cost-effective wind, solar and hydro renewable energy, the new Marinus link and supporting transmission will provide dispatchable energy to Australia when it's needed.

Marinus Link Route

The Acumentis Compulsory Acquisition and Compensation team, led by Craig McMillan will support the project by working with Marinus, landowners, and businesses through the acquisition of land and easements for the transmission land cables in Victoria.

Craig McMillan, Acumentis Group Executive Director - Commercial & Advisory said, "Acumentis is thrilled to play a role in the Marinus Link project, supporting the delivery of much-needed clean energy to the national grid. It's such a critical project in securing energy and transitioning to net-zero by 2050."

"We're pleased to have been selected to provide easement valuation and acquisition services building on our team's expertise in this space. We look forward to working with the Gippsland and Victorian communities and businesses to achieve positive outcomes for all," he said.

The project is currently in the design and approvals phase where the landowner and community engagement, land and easement acquisition are required to finalise the proposed route before any construction can commence. With a 4-7 year manufacturing and construction phase it is hoped that the Marinus link will be operational by 2030.

Acumentis operates a nationwide specialist infrastructure and acquisition projects group. This specialist team provides valuation and land acquisition expertise to constructing authorities, government departments, corporations, and the resource industry at large.

The team has extensive experience in the assessment of compensation for the acquisition of easements and whole properties having worked on many energy, road and rail corridors, mining and petroleum projects.

Attachments

  • Original Link
  • Original Document
  • Permalink

Disclaimer

Acumentis Group Limited published this content on 01 July 2022 and is solely responsible for the information contained therein. Distributed by Public, unedited and unaltered, on 01 July 2022 02:02:05 UTC.