ENCOURAGING PROGRESS AT
          AFRICAN EAGLE'S DUTWA NICKEL PROJECT IN TANZANIA

 Drilling programme started and metallurgical testwork well advanced


*                      Drilling programme underway
*                      Phase two metallurgical testwork well advanced
*                      Updated resource estimate expected Q1 2010
*                      Recruitment in progress of a Project Manager
  for Dutwa

African Eagle's  Managing  Director  Mark Parker  comments,  "We  are
pleased to report significant progress  at our exciting Dutwa  Nickel
Project in  Tanzania.  Our  120-hole RC  drilling  programme  is  now
underway and laboratory testwork is well advanced.  We have chosen  a
contractor for a  transport and  logistics study and  will appoint  a
contractor for advanced deposit modelling shortly."

"We have  also  advertised  for  a Project  Manager  with  a  process
metallurgical  background,  one  of  a  number  of  recruitments  and
management changes  required  to  transform  African  Eagle  from  an
exploration group into a nickel development and mining company."


The Dutwa Scoping Study, delivered in July, made a strong  investment
case for the project, indicating a likely Internal Rate of Return  of
about 25% at the current nickel price of around US$8.50/lb, or 17% at
the base case price of US$7/lb. Net Present Value estimates at  these
nickel prices  were  US$530  million  and  US$200  million  (pre-tax)
respectively.

The Study  identified  several  key  areas  which  could  have  major
positive impacts  on  the economics  of  the project.  These  include
increasing the global  resource by delineating  the adjacent  Ngasamo
deposit, determining  the  optimum processing  method  by  conducting
further metallurgical testwork, and reducing the cost of transporting
chemical reagents to the mine site.

Through a successful Offer and Placing in August, the Company  raised
£3.3 million additional  capital to fund  these studies and  progress
the project towards feasibility.

Drilling and deposit modelling

African Eagle has now  begun a programme  of approximately 60  infill
and step-out  drill holes  on the  main nickel  deposit at  Wamangola
Hill, with  the objective  of increasing  the JORC  Inferred  Mineral
Resource of 31  million tonnes at  an average grade  of 1.1%  nickel,
estimated by  SRK in  November 2008.  The drilling  should allow  the
resource to be delineated to Indicated category.

After completion of this programme, drilling will move to the  nearby
Ngasamo Hill, which has a laterite blanket similar to Wamangola  Hill
and affords  the  opportunity to  increase  the current  resource  by
another 15-20 million tonnes. African Eagle is in joint venture  with
Safina a.s. of  the Czech Republic,  owners of the  mineral title  to
Ngasamo Hill, and can earn a 75% interest by including Ngasamo in the
global feasibility study.

An independent consultant  will be  contracted shortly  to carry  out
deposit modelling and mine planning on the drill results.

Metallurgical Testwork

Another 250 kilograms  of drill  core has been  despatched to  Mintek
laboratories in South  Africa for the  second phase of  metallurgical
testwork, which includes tank and  column leach tests, rock  strength
and abrasion measurements  and agglomeration tests.   This work  will
help to  determine  the  best extraction  process  and  optimise  the
parameters such  as  acid  concentration, residence  time  and  leach
temperature.

Once the results of the phase  two testwork are in hand, the  Company
plans to undertake  more diamond  drilling to provide  a further  one
tonne of drill core for advanced metallurgical testwork.

Transport Study

Transport and logistics  costs will be  a significant contributor  to
overall operating costs and the  Company is currently assessing  bids
to conduct a detailed investigation into the transport alternatives.
The study will examine port options and road, rail and lake transport
in both  Tanzania and  Kenya, with  the aim  of minimising  transport
costs.

Project Manager

African Eagle  has  begun  the  process  of  transformation  from  an
exploration group into a nickel  development and mining company.  New
staff will  be recruited  to  bring in  the  skills needed,  and  the
Company is currently advertising for a Project Manager with a process
metallurgical background and project management experience.   Details
of the post are available on the Company's web site and in the mining
press.



Technical terms
A  glossary  of  technical  terms  used  by  African  Eagle  in  this
announcement  and   other  published   material  may   be  found   at
www.africaneagle.co.uk/p/glossary.asp


For further information:

Mark Parker
Managing Director
African Eagle
+44 20 7248 6059
+44 77 5640 6899

Nicola Marrin
Seymour Pierce Limited, London
Nominated Adviser
+ 44 20 7107 8000

Charmane Russell
Russell & Associates, Johannesburg
+ 27 11 8803924
+27 82 8928052

Ed Portman / Leesa Peters
Conduit PR, London
+44 20 7429 6607
+44 77 3336 3501


About African Eagle

African Eagle is  a diversified mineral  exploration and  development
company operating  in  eastern  and  central  Africa.  The  Company's
principal advanced assets are the Dutwa nickel laterite discovery  in
Tanzania, where the Company completed  a scoping study in June  2009,
and its 49% interest in the Mkushi Copper Mines joint venture project
in Zambia, for which  a draft feasibility study  was completed in  Q4
2008.

African Eagle  is  evaluating  a  second  promising  nickel  laterite
deposit at Zanzui in  Tanzania and has defined  a JORC gold  resource
estimated at half  a million  ounces at  its Miyabi  gold project  in
Tanzania. The Company  holds a well-balanced  portfolio of  promising
earlier stage gold, copper, platinum and uranium projects,  including
the Ndola  and Mokambo  projects in  the Zambian  Copperbelt and  the
Igurubi gold project in Tanzania.

Zambia,  Tanzania  and  Mozambique,  the  sites  of  African  Eagle's
projects, are all  countries which have  highly prospective  geology,
relatively low  above-ground risks  and track  records of  successful
major investments in the metals and minerals industries.

In December  2008, African  Eagle resolved  to prioritise  the  Dutwa
project, because  the  Board  believes that,  of  all  the  Company's
projects, it offered the greatest potential to add value. To take its
other discoveries into production, African Eagle is seeking  industry
partners with records  of successful  mine development,  by means  of
joint ventures, farm-ins, spin-outs or other mechanisms.

About the Dutwa Project

African Eagle has discovered a significant nickel laterite deposit in
the Dutwa  project  area  in the  Lake  Victoria  Goldfield.   Within
Tanzania, the  project  is  favourably situated  100km  east  of  the
railhead at Mwanza and close to the main Mwanza-Nairobi trunk road, a
major power line and the shore of Lake Victoria.

The Company holds a 90% interest,  with option to acquire 100%,  over
the Dutwa laterite deposit and in 2009, signed a Letter of Intent for
an option and joint venture over another nickel laterite at  Ngasamo,
5km west. In  all, African Eagle  has explored a  total area of  more
than 750km² in the project area.

Since the discovery of the Dutwa nickel deposit in June 2008, African
Eagle has  explored the  project very  quickly and  cost-effectively,
including resource  drilling and  an independent  resource  estimate;
laboratory metallurgical and mineralogical tests which revealed  that
the  deposit  could  be  processed  efficiently  by  sulphuric   acid
leaching.  On 24 June 2009, the Company announced the results of  its
"proof of concept" scoping study. The study, by GRD Minproc of Perth,
Western Australia,  indicated that  the project  can be  economically
viable, and African  Eagle has  now begun work  towards a  definitive
feasibility study.

The Study indicates that Dutwa, if it were in production today, would
be profitable. Earnings, on an EBIT  basis, would be of the order  of
$110 million per annum  on average over the  life of mine, giving  an
internal rate of return around 20%.

As a potentially low-cost producer, the upside for the Dutwa  project
is considerable if nickel prices are above the $7/lb used in the base
case.  The following table shows  the key metrics for several  upside
cases.


Ni price          US$/lb  9.00  8.50  8.00  7.50  7.00  6.50
Life of mine EBIT   $M   2,600 2,300 2,000 1,800 1,500 1,200
Pre-tax IRR         %       31    27    24    21    17    13
Post-tax IRR        %       27    24    21    18    15    11
Pre-tax NPV         $M     640   530   420   310   200    90
Post-tax NPV        $M     430   350   270   190   110    30





Base case:                                 Abbreviations:

Nickel price = US$ 7/lb ($15,430/tonne)    EBIT = Earnings before
Cobalt price = US$ 10/lb                   interest and tax
Discount rate = 10%                        IRR = Internal Rate of
Transport cost = US$100/tonne              Return
(8¢/tonne/km)                              NPV = Net Present Value
Tax rate = 30%, fiscal incentives not      DCF = Discounted cash flow
accounted                                  analysis
Royalty = 3%
                                           All numbers stated to 2
The financial modelling was conducted in   significant digits
US dollars with an estimated accuracy of
±30%




The Study adopted a fairly broad brush approach to many of the costs,
to demonstrate "proof of concept" and provide indicative  economics.
GRD Minproc estimated  individual capital  and operating  costs to  ±
30%, based on  their considerable experience  with nickel  laterites.
These variables will be determined with more accuracy and  confidence
during the forthcoming feasibility work.

The Study identified  several key  areas where  further testwork  and
detailed study are especially likely to result in improvements to the
"bottom line"  or  to important  gains  in confidence.   These  areas
include:

*        Improved global deposit model and the potential for early
  "high-grading".  The Ngasamo resource will be drilled and
  incorporated into a more sophisticated global resource model and
  mining plan.  From this, it will be possible to establish whether
  richer ore can be mined first, giving increased early cash-flow and
  an improved NPV.
*        Ore beneficiation and project scale. The capital and
  operating costs of the plant would be reduced if mechanical
  beneficiation of the ore prior to leaching yields a smaller tonnage
  of richer material for processing through the plant.
*        Advanced leaching testwork. Column and vat leach tests at
  bench and pilot scale will determine the best operating conditions
  to optimise nickel extraction, including acid concentration,
  residence time and temperature.
*        Reagent cost reductions.  The cost of reagents, notably
  sulphur and lime, will be a significant component of operating
  costs and profitability will increase considerably if these costs
  are minimised.  Transport is a substantial part of the reagent
  costs and ways to minimise this will be investigated, as will the
  availability of more local sources, particularly of lime.
*        More sophisticated fiscal and economic modelling.  Tanzania
  offers a number of tax incentives for exploration and mine
  development, which were not fully accounted in the Study economic
  model.

In August,  the Company  raised £3.3M  additional capital  through  a
Placing and Offer, to address  these issues and progress the  project
towards feasibility.  Further metallurgical testing has commenced  on
drill core samples  at Mintek  laboratories in South  Africa and  the
Company has started infill drilling at Dutwa and resource drilling at
Ngasamo.

African Eagle acquired the Dutwa project for its gold potential,  but
the Company's  exploration team  quickly  recognised that  there  was
significant nickel laterite potential. There is very little  outcrop,
so the Company conducted extensive ground magnetic surveys to  reveal
the underlying  structure  and  geology. The  Company  also  compiled
historical  data,  including  detailed  geological  maps  and  trench
results dating from 1956,  when rock chip  samples from the  trenches
over the  ultramafic  rocks were  reported  as yielding  up  to  1.9%
nickel.

Greenstones and granites underlie the project area. The  greenstones,
of Archaean  Nyanzian  age,  are mostly  metamorphosed  volcanic  and
sedimentary rocks,  with  some banded  iron  formation in  the  east.
Several large ultramafic bodies occur within the greenstones and  the
nickel laterites form a blanket up to 60m thick on top of these.

To investigate  the nickel  discovery,  the Company  undertook  trial
drilling in  June  2008. The  results  were very  encouraging  and  a
139-hole reverse circulation (RC) drilling programme was completed to
delineate the  resource.  African  Eagle  also  undertook  a  10-hole
diamond drill  programme to  obtain  core samples  for  metallurgical
testing and density measurements.

In November 2008, African Eagle announced an initial Inferred Mineral
Resource estimate of 31  million tonnes at an  average grade of  1.1%
nickel and 0.034%  cobalt. At a  cut-off grade of  0.5% nickel,  this
gives Dutwa a  contained metal  endowment of some  340,000 tonnes  of
nickel and 11,000  tonnes of  cobalt.  The estimate  was prepared  by
independent consultants  SRK Consulting  (UK) Ltd  in line  with  the
Australasian Code for Reporting of Mineral Resources and Ore Reserves
(the JORC  Code).  A little  additional  drilling and  more  advanced
geostatistics and deposit  modelling will  be needed  to upgrade  the
resource to Indicated category.

Ngasamo Hill, 5km  west of  the Dutwa deposit,  is geologically  very
similar and holds a laterite deposit of the order of 15 to 20 million
tonnes, which would increase  the global resource  at Dutwa from  the
currently defined 31 million tonnes at  1.1% nickel, to some 45 -  50
million tonnes.  Drilling and metallurgical  tests will be needed  to
confirm the  size, grade  and compatibility  of Ngasamo.   Under  its
agreement with Ngasamo's owners, (Safina  a.s. of the Czech  Republic
and its Tanzanian subsidiary  Precious Metals Refinery Company  Ltd),
African Eagle can earn an interest of  at least 50% and up to 75%  in
Ngasamo by  carrying out  exploration and  evaluation work,  up to  a
feasibility study.

Mintek Laboratories in Johannesburg  investigated the mineralogy  and
metallurgy of mineralised drill  samples from the deposit,  including
extended 'bottle  roll' sulphuric  acid  leach tests  to  investigate
metal recoveries  and  acid  consumption.  Mintek  also  carried  out
mineralogical characterisation by  X-ray diffraction (XRD),  scanning
electron microscopy (SEM) and polished section work.

The bottle roll test results showed nickel extractions of 70-90% with
an average of 83%.  Cobalt extractions were mostly in the range 70 to
85%. The acid consumptions, averaging 209kg/t, are very low  compared
to other Ni laterite ores worldwide.

The mineralogical investigations show that the laterite is  extremely
silica-rich, with  low iron  and magnesium  content, indicating  that
Dutwa is not a typical laterite nickel deposit.  Mintek believes that
much of the nickel and cobalt occurs in "wad" with manganese  content
of 20-60%, nickel content of  up to 20% and  cobalt content of up  to
10%.

The unusual mineralogy  of the  deposit is highly  beneficial, as  it
results in lower acid consumption and  is expected to give good  heap
leach permeability  or  favourable liquid-solid  separation  in  tank
leaching. The concentration of nickel and cobalt in the manganese wad
offers  the  possibility  that  mechanical  selection  of  high-grade
material  may  allow  reduced  throughput  and  hence  a  lower  cost
processing plant.

The Company  is also  investigating other  potential nickel  laterite
deposits in  Tanzania, and  has  completed a  trial programme  of  RC
drilling to test a laterite at its Zanzui project, 60km to the  south
of Dutwa.   Results included  42m at  1.05% nickel  (including 6m  at
2.80%) and 33m at 0.91% nickel (including 9m at 1.41%).

---END OF MESSAGE---


This announcement was originally distributed by Hugin. The issuer is 
solely responsible for the content of this announcement.



Copyright © Hugin AS 2009. All rights reserved.