Ecolomondo Corporation announced that the three major processing departments at the Hawkesbury TDP facility have completed pre-commissioning and have entered into final commissioning. Tire Shredding line - final commissioning is complete and initial operation runs to begin first week of April. Recovered Carbon Black line - pre-commissioning was completed at the end of February and the line is undergoing final commissioning and expected to be completed in the second week of April.

Thermal Processing line - pre-commissioning began late-February and is now complete, final commissioning is underway and expected to be completed by the second week of April 2022 with trial runs to commence soon thereafter. Automation interfacing with all processing control panels is going according to schedule and should be completed by the second week of April. The Company expects to begin preliminary operations in the next 3 to 4 weeks, gradually ramping up to full production volumes over 10 to 12 weeks.

Full production is defined by the company as 3 shifts operating the plant on a continuous basis. As recently announced the company has received a combination of purchase orders and off-take agreements' for the high-quality oil, recovered carbon black and steel that will be produced at the Hawkesbury TDP facility.