July 27, 2021

Electric Power Development Co., Ltd. (J-POWER)

Renewal Works of Sarakitomanai Windfarm Have Started

The third renewal project for J-POWER Group's domestic wind power

Electric Power Development Co., Ltd. (hereafter "J-POWER") announces that J-Wind Co., Ltd., a wholly owned subsidiary of J-POWER, has begun renewal works at Sarakitomanai Windfarm in Hokkaido, Japan.

This project is the third renewal project for J-POWER Group's wind power business following Shimamaki Windfarm which has been under renewal works since May 2021.

Sarakitomanai Windfarm had been in commercial operation for 20 years since December 2001. In this renewal project, nine existing aged wind turbines, of which capacity is 1,650kW for each, will be replaced with four 4,300kW wind turbines, which stands at the largest level in Japan.

After its planned commercial operations in January 2024, the high performance of the cutting- edge large-scale wind turbine is expected to enable utilizing the wind resources at the site as much as possible.

J-POWER Group continues initiatives to replace aged wind turbines all over Japan in order to achieve sustainable development of renewable energy and stable operations.

1. Overview of the windfarm

Name

New Sarakitomanai Windfarm

Location

Wakkanai city, Hokkaido, Japan

Capacity

14,850kW (Siemens Gamesa 4,300kW turbine x 4)

Schedule

July 2021

Commencement of construction

January 2024

Commencement of commercial Operations (planned)

2. Location map

Sarakitomanai Windfarm

Current status of the windfarm

Appendix: J-POWER Group's windfarms

As of July 27, 2021

Capacity

Capacity of

Number of

Commencement of

Location

Name

each wind turbine

commercial

(kW)

wind turbine

(kW)

operations

In operation (Japan)

1

Akita

Nikaho Kogen

24,750

1,650

15

Dec. 2001

2

Hokkaido

Saraki Tomanai Wind Farm

14,850

1,650

9

Dec. 2001

3

Tokyo

Tokyo Bayside

1,700

850

2

Mar. 2003

4

Kagoshima

Minami Oosumi

24,700

1,300

9

Mar. 2003 (Neshiko)

1,300

10

Mar. 2004 (Sata)

5

Yamaguchi

Yokihi no Sato Wind Park

4,500

1,500

3

Nov. 2003

6

Iwate

Green Power Kuzumaki

21,000

1,750

12

Dec. 2003

7

Aichi

Tahara

1,980

1,980

1

Mar. 2004

8

Nagasaki

Nagasaki-Shikamachi Wind Farm

10,500

1,000

15

Feb. 2005

9

Kumamoto

Aso-Nishihara Wind Farm

17,500

1,750

10

Feb. 2005

10

Aichi

Tahara Bayside

22,000

2,000

11

Mar. 2005

11

Hokkaido

Setana Seaside

12,000

2,000

6

Dec. 2005

12

Fukushima

Koriyama-Nunobiki

65,980

2,000

32

Feb. 2007

1,980

1

13

Kumamoto

Aso-Oguni Wind Farm

8,500

1,700

5

Mar. 2007

14

Shizuoka

Irouzaki

34,000

2,000

17

Apr. 2010

15

Fukui

Awara-Kitagata

20,000

2,000

10

Feb. 2011

16

Fukushima

Hiyama Kogen

28,000

2,000

14

Feb. 2011

17

Hokkaido

Kaminokuni Wind Farm

28,000

2,333

11

Mar. 2014

2,337

1

18

Ehime

Minami Ehime

28,500

2,400

9

Mar. 2015

2,300

3

Apr. 2016

19

Aomori

Ohma Wind Farm

19,500

2,300

9

May 2016

20

Akita

Yurihonjo Bayside

16,100

2,300

7

Jan. 2017

21

Hokkaido

Setana-Osato

50,000

3,200

16

Jan. 2020

22

Akita

Nikaho No.2

41,400

2,300

18

Jan. 2020

23

Iwate

Kuzumaki No.2

44,600

2,000

16

Dec. 2020

2,100

6

Japan total (in operation)

540,060

Under construction (Japan)

24

Hokkaido

Kaminokuni No.2

41,532

4,300

10

FY 2022 (planned)

Japan total (in operation/under construction)

581,592

Under construction (Renewal)

25

Hokkaido

New Tomamae Winvilla

30,600

4,300

8

FY2022 (planned)

26

Hokkaido

New Shimamaki

4,300

4,300

1

2022 (planned)

Japan total (in operation/under construction includes renewall)

616,492

Under construction (overseas)

27

U.K.

Triton Knoll

214,250

9,500

90

2021 (planned)

Global total (in operation/under construction)

830,742

*Sarakitomanai Windfarm continues to operate in commercial operation until Feburuary 2022 though it started renewall works.

  • As for Nagasaki-Shikamachi Wind Farm, total capacity is 15,000kW while owned capacity is 10,500kW as J-POWER Group's interest is 70%
  • As for Triton Knoll, total capacity is 857MW while owned capacity is 214,250kW as J-POWER Group's interest is 25%