Heron Resources Limited provided the update on the company's wholly owned Woodlawn Zinc-Copper Project in New South Wales, Australia. Significant progress continues to be made at the site, and the commencement of underground activities by Pybar Mining Services (Pybar) marks a significant milestone in the project development schedule. Construction is progressing on track to commence commissioning by the end of the year. Reclaimed Tailings Mining: At Tailings Dam South (TDS), an internal wall has been constructed and a storage dam created to provide a water source for hydraulic mining operations. Hydraulic mining equipment infrastructure is being installed adjacent to the dam and the mining of reclaimed material from TDS will provide the first ore for commissioning of the processing plant. Engineering, Procurement & Construction: Sedgman continues to advance the EPC works at the main process and paste plant sites in accordance with the project timeline. Current activities are focused on equipment installation, piping and electrical wiring. Almost all major items of equipment have now been delivered to site. The project construction progress measures at the end of August were: Overall Project (73% complete); Earthworks (substantially completed); Equipment Purchase (98% complete); Concrete (substantially complete) and offsite Fabrication (92% complete).