Ironbark Zinc Limited updated its shareholders with respect to ongoing permitting at its flagship Citronen Project in Greenland. Highlights: Ironbark is now in receipt of its Section 19-43 Permit which sets out the exploitation plan and closure requirements for the Citronen Project from the Government of Greenland; In the board's opinion, this is the last permit required before a final investment decision is made to proceed at Citronen in 2021; The approval ends the 9 year long permitting process covering Ironbark's Exploitation License approval (2011-2016) and subsequent Section 19-43 (Exploitation and Closure Plan) approval (2016-2020), and is yet another major achievement by the company in 2020.