October 1, 2014
T he Meta l s Pro d uct i o n Pla n s i n t he 2nd Half o f the f isc a l year e n din g M arc h 31, 2015The planned productions in the 2nd half of the fiscal year ending March 31, 2015 are
as follows:
Period | September 2014 to March 2015 |
Refined Copper | 23,633 metric ton per month |
Refined Lead | 2,493 metric ton per month |
Refined Gold | 3,817 kg per month |
Refined Silver | 29,833 kg per month |
(Reference)
April 2014 to September 2014 (previous 6 months) | October 2013 to March 2014 (year-on-year) | |
Refined Copper | 26,608 metric ton per month | 26,523 metric ton per month |
Refined Lead | 2,480 metric ton per month | 2,461 metric ton per month |
Refined Zinc | - | 635 metric ton per month |
Refined Gold | 3,708 kg per month | 2,488 kg per month |
Refined Silver | 30,667 kg per month | 28,420 kg per month |
Notes on year-on-year comparison
Copper
• At Naoshima Smelter and Refinery, periodic maintenance shutdown is planned for the period, contributing to a decrease of production. At Onahama Smelter and Refinery, the production will drop due to a decrease of receiving anodes shipped from
Naoshima Smelter and Refinery. As a consequence, the total production of refined copper will decrease approximately by 11%.
Gold/Silver
• Refined gold production will increase due to an increase of treatment of raw materials and its higher content of gold.
• Refined silver production will increase due to an increase of treatment of raw materials.