March 21, 2024 | PTL/Corp/PSX/14 |
The General Manager
Pakistan Stock Exchange
Stock Exchange Building
Stock Exchange Road
Karachi,
Dear Sir,
Final Progress Report as of December 31, 2023
We are pleased to submit the final progress report as of December 31, 2023, along with the Agreed Upon Procedures' Report as issued by our Auditors, M/S KPMG Taseer Hadi & Co, on the implementation status of the project. This progress report is being submitted in compliance with the requirement of Clause 16(ii)(a) of post-issue reporting and disclosures of the "Public Offering Regulations, 2017" and in pursuance of the requirement specified in clause 4.1.10 of the prospectus to the issue of the Company.
Yours truly,
__________________
Company Secretary Mohsin Muzaffar Butt
CC:
Executive Director/HOD,
Offsite-II Department,
Supervision Division,
Securities & Exchange Commission of Pakistan,
63, NIC Building, Jinnah Avenue, Blue Area,
Islamabad.
PROGRESS REPORT
PANTHER TYRES LIMITED
FINAL PROGRESS REPORT
31 DECEMBER 2023
(AS REQUIRED BY REGULATION 16 OF THE PUBLIC OFFERING
REGULATIONS 2017).
P a g e 1 | 9
PROGRESS REPORT
TABLE OF CONTENTS
PREAMBLE……..……………………………………………………………………………………………………………3
IPO PROCEEDS…………………………………………………………………………………………………………..…3
IMPLEMENTATION STATUS………………………………………………………………………………………….4
ANNEXURE-I………………………………………………………………………………………………………………..8
P a g e 2 | 9
PROGRESS REPORT
PREAMBLE
We are pleased to submit the final progress report as of December 31, 2023, along with the Agreed Upon Procedures' Report as issued by our Auditors, M/S KPMG Taseer Hadi & Co, on the implementation status of the project. This progress report is being submitted in compliance with the requirement of Clause 16(iia) of post-issue reporting and disclosures of the "Public Offering Regulations, 2017" and in pursuance of the requirement specified in clause 4.1.10 of the prospectus to the issue of the Company.
The Company carried out an IPO in February 2021 to partially finance its major expansion project. A sum of Rs.1.410 billion was allocated to this expansion from IPO proceeds as per detail below:
Description | Funds Required (PKR) | ||||
Plant and Machinery | |||||
4 Roll Calendar Line Comerio Italy | 586,310,100 | ||||
Banbury Tangential Mixer | 328,629,670 | ||||
Freehold Land & Development Expenses | 100,000,000 | ||||
Building and Civil Works | |||||
Building for Calendar Department | 166,780,230 | ||||
Building for Mixing Department | 167,880,000 | ||||
Building for Tube Department | 60,400,000 | ||||
Total | 1,410,000,000 |
SUMMARY OF IPO PROCEEDS
The Company had raised funds through the issuance of 30 million ordinary shares at a strike price of Rupees 65.80 per share as per detail given below:
Description | Amount (PKR) | ||||
Issuance of 30,000,000 ordinary shares at the strike price of Rs.65.8 per | 1,974,000,000 | ||||
share | |||||
Less: IPO expenses | (99,566,342) | ||||
Net IPO proceeds | 1,874,433,658 | ||||
Less: Funds Utilized to pay off Working Capital Loan (Ref clause 4.1.8) | *(464,433,658) | ||||
Net Funds available for expansion | 1,410,000,000 |
*The excess funds amounting to Rupees 464.43 million received through IPO were utilized to reduce the short-term working capital lines as per clause 4.1.8 of the prospectus.
P a g e 3 | 9
PROGRESS REPORT
IMPLEMENTATION STATUS
The status of the expansion project as of the close of December 2023 is given below in prescribed format:
Funds | Actual | ||||||||||
Allocation | Expenditures | ||||||||||
Description | Required | ||||||||||
% | as on 31 Dec, | ||||||||||
(PKR) | |||||||||||
2023 (PKR) | |||||||||||
Freehold Land & Development Expenses | 100,000,000 | 7.10% | 101,021,403 | ||||||||
Building and Civil Works | |||||||||||
Building for Tube Department | 60,400,000 | 4.30% | 60,810,689 | ||||||||
Building for Calendar Department | 166,780,230 | 11.80% | 163,095,182 | ||||||||
Building for Mixing Department | 167,880,000 | 11.90% | 369,216,985 | ||||||||
Plant and Machinery | |||||||||||
4 Roll Calendar Line Comerio Italy | 586,310,100 | 41.60% | 770,263,898 | ||||||||
Banbury Tangential Mixer | 328,629,670 | 23.30% | 521,593,400 | ||||||||
Total | 1,410,000,000 | 100% | 1,986,001,557 |
Implementation status of each project is being given below separately:
LAND AND DEVELOPMENTS
This land is located adjacent to the existing land of the factory located at 29.4 KM Sheikhupura Road. The acquisition process of this land is already complete.
Start date | Completion date | |||||||||||||
Commitment made in the | (disclosed in | Rationale for | ||||||||||||
(disclosed in the | Current status | |||||||||||||
prospectus | the | delay, if any | ||||||||||||
prospectus) | ||||||||||||||
prospectus) | ||||||||||||||
Acquisition of land | 1Q FY 2021 | 3Q FY 2021 | 100% | Project | ||||||||||
Complete | completed | |||||||||||||
BUILDING AND CIVIL WORKS
Following are the three buildings which were to be constructed through IPO funds:
P a g e 4 | 9
PROGRESS REPORT
Start date | Completion date | Current | Rationale | |||||||||||
Commitment made in the prospectus | (disclosed in the | (disclosed in the | for delay, if | |||||||||||
status | ||||||||||||||
prospectus) | prospectus) | any | ||||||||||||
Refer to | ||||||||||||||
Tube department Building | 3Q FY 2021 | 4Q FY 2021 | 100% | sub | ||||||||||
Complete | section | |||||||||||||
'a' | ||||||||||||||
Refer to | ||||||||||||||
Calendar department Building | 4Q FY 2021 | 2Q FY 2022 | 100% | sub | ||||||||||
Complete | section | |||||||||||||
'b' | ||||||||||||||
Refer to | ||||||||||||||
Mixing department Building | 3Q FY 2021 | 2Q FY 2022 | 100% | sub | ||||||||||
Complete | section | |||||||||||||
'c' |
a) MC Tube Building
This was an extension of the existing building of the motorcycle tube section, which was completed in FY2022. The completion of this building got delayed because the listing process took more than expected time.
b) Calendar Building
This building has been constructed to accommodate the newly acquired calendaring line. The work on the building is finished, and the project is 100% complete. Since, the arrival of calendaring line was delayed, the civil work was put on hold which caused the delay of time line as disclosed in the prospectus.
c) Mixing Building
This is a new state-of-the-artmulti-story building designed to accommodate recently acquired automated mixing lines. Civil and other related work on the project is 100% complete.
The above table shows a substantial increase in the cost of the project from Rs.167 million to Rs.369 million. As per the initial layout finalized prior to IPO, the building was planned to accommodate two mixing lines and the construction cost was estimated at Rs.167 million. Subsequently, on the advice of the technical team, the building design/area was changed to accommodate the four mixing lines. This resulted in an extended scope of work and an escalation of the cost of the building to Rs.369 million. Enhanced scope of work took more than originally planned time and hence affected the projected completion date. The change in scope and overall cost escalation was duly approved by the Board.
PLANT AND MACHINERY
Plant & machinery financed through IPO include the 4 Roll Calendar Line and Banbury Tangential mixer, along with accessories.
The implementation status of these machines is given as follows:
P a g e 5 | 9
Attention: This is an excerpt of the original content. To continue reading it, access the original document here. |
Attachments
- Original Link
- Original Document
- Permalink
Disclaimer
Panther Tyres Ltd. published this content on 21 March 2024 and is solely responsible for the information contained therein. Distributed by Public, unedited and unaltered, on 21 March 2024 09:06:04 UTC.