Highlights
- 20 Litres of brine was extracted 18 metres away from hole 16 at Cilon where the brine was assayed at 1,122ppm Lithium* at 707024.4E 7409988.8N.
- Four assays of the brine collected were assayed at an arithmetic average of 308.57 ppm Li using a Turbospec E400 analyser for lithium and boron.
- The highest extraction rate achieved by Ekosolve(TM) has been approximately 96% Lithium using the Ekosolve(TM) technology for brines sampled at Pocitos 7, Pocitos Salar that averaged 97ppm (Pocitos 7 is not an asset of PL3).
- The brines have been received and tests will be conducted at the
* ASX release dated
The Ekosolve(TM) system uses approximately 2,400L of fresh water for every one tonne of 99.5% purity lithium chloride produced. See www.ekosolve.com.au **for more information.
The brines will undergo several tests with various concentrations of solvents to brines and lithium yields will be maximised as the data is assembled. A full report will be produced which will assist in the pre-engineering studies once a resource is identified from drilling.
*To view tables and figures, please visit:
https://abnnewswire.net/lnk/4X8T1E11
About
Contact:
Executive Chairman
M: +61 433 747 380
E: phil@patagonialithium.com.au
Copyright (C) 2023 ABN Newswire. All rights reserved., source