Pinnacle Minerals Ltd. announced that a 52-hole drilling program is confirmed at the Companies 100% owned Tambellup East Project ("Project"), with the drilling team mobilising to site on the 23rd March 2023. The aim of the program is to delineate additional kaolin resources to add to potential inventory. Experienced air-core drilling contractors Sahara have been engaged for the work which is expected to take approximately nine days.

The program is to be conducted across a large 1.8km2 area that has several bright white "kaolin" dams, indicating that kaolin mineralisation is at or near surface. Whilst the program is underway, elevated nickel geochemical results previously identified by Falcon Mining in 2008 will also be tested via drilling to basement /bit refusal and conducting a multi-element analysis of the end of hole core. The footprint of the drilling program encompasses an area equivalent to the Hulls Resource which forms part of the Tambellup Kaolin Resource which has a Mineral Resource Estimate (MRE) of 12.5Mt Kaolinised Granite.