By the results of 3 quarters of 2015 power engineers of 'IDGC of the South' PJSC (Rosseti group of companies) have commissioned 27 MVA of transformer capacity, constructed and modernized 208 kilometres of power lines.

The growth of capital investments towards the planned indicators can be explained by construction of facilities and buildings that need technological connection to electric networks of IDGC of the South.

In order to connect the beneficiary category of consumers, our power engineers constructed grid facilities for the total amount of 140 million rubles.

In the 4th quarter the Company plans to commission another capital construction project -110/35/10kV substation 'Chertkovskaya' with rearranging of 110/35/10 kV feeders.

Also by the end of the year the Company plans to accomplish a project in Rostov-on-Don: 'Reconstruction of power line 'Koisug - R31 - R16 - PP2 -R22' and 110kV power line 'R23 - R2 - PP2 - R22' with replacement of a section of the power lines to a new route'. Its successful implementation will enhance reliability and safety of power supply to homes and businesses in the central part of Rostov-on-Don.

All projects of the Company's investment programme will not only guarantee reliable power supply to customers, but will create favourable conditions for social and economic development of four region of Company's presence.