Medium-Term Strategy for Electric Power Cable
Sumitomo Electric Industries, Ltd.
November 13, 2023
1. Electric Power Cable Business Unit - Overview and Medium-Term Targets 2/10
(1) Overview | (2) Medium-Term Targets |
- Electric Power Cable Unit Results for FY 2022
Sales ¥200 billion
- Major Products
Electric Power | Engineering | Distribution | Overhead | |||
Cable | Accessories | Conductors | ||||
FY2030
Aim for sales of 150% or more and operating
profit of 200% or more compared to FY2022
- Sites
Foreign | Domestic |
Ibaraki Works
SEUK-CL (UK)
Submarine Cable | Itami |
(Established May,2023) | SEI-Futong |
(Hangzhou)
Accessories
JPSS (Saudi
Arabia)
Submarine
Cable
Osaka Works
F-JPS (India)
High-Voltage Cable | SIK (Indonesia) |
Electric Power Cable
Business Unit
Sales / Operating Profit
Land
Sub-
marine
150% or more
Sales
200% or more
Operating
Profit
Low and Middle Voltage Cable
FY2020 | FY2022 | FY2025 | FY2030 |
2. Market Environment and Priority Initiatives | 3/10 |
Increase in renewable energy investment has expanded the demand for DC interconnectors and offshore wind power. Demand for domestic equipment renewal has been steady.
Strengthening manufacturing and installation capacity, mainly in Europe and Japan, to capture growing demand.
Market Environment | Priority Initiatives |
DC Interconnectors | Europe: Increase manufacturing and | ||
Compared | Europe: Rapid growth and | ||
About 400% | installation capacity | ||
to 2022 | Other | reinforcement of DC | Cooperation with Siemens |
interconnectors | |||
Japan | Japan: DC interconnection line project | ||
100% | Japan: As renewable energy expands, | Development: High-performance insulation | ||||||||||||||||
Europe | ||||||||||||||||||
materials | ||||||||||||||||||
future demand for | ||||||||||||||||||
Protection Engineering method | ||||||||||||||||||
interconnectors will gain speed | ||||||||||||||||||
2022 | 2030 | |||||||||||||||||
Offshore Wind | ||||||||||||||||||
Compared to 2022 | Renewable energy is expanding to | |||||||||||||||||
About 600% | ||||||||||||||||||
achieve decarbonization | Europe: Augment production capacity | |||||||||||||||||
United | ||||||||||||||||||
States | Japan: Transmission package with | |||||||||||||||||
Europe | Installation of offshore wind is | Nissin/Densetsu | ||||||||||||||||
100% | accelerating mainly in Europe and | Development:Larger scale / Floating type | ||||||||||||||||
China | ||||||||||||||||||
Japan | China | |||||||||||||||||
2022 | 2030 | |||||||||||||||||
Domestic Market | ||||||||||||||||||
Compared to 2022 | ||||||||||||||||||
100% About 110 | % | Demand is at a high level due to the | Long-term partner contracts | |||||||||||||||
updating of aging equipment | Augment construction capabilities | |||||||||||||||||
Many long-term contracts with | ||||||||||||||||||
partners | Continue to introduce distinct products | |||||||||||||||||
2022 | 2030 | |||||||||||||||||
3. DC interconnectors | 4/10 |
Acceleration of interconnection line reinforcement. There is a move toward preferential local content in response to increased demand for DC cables and from the perspective of energy security. We will also establish a base in Europe.
(1) Market Trends
■Europe
・Accelerated construction of national and interregional interconnection lines.
・Plans are being developed to reinforce European power grids
(~FY2040, 70,000 km cable length)
(2)Our Projects * indicates collaboration with Siemens (Germany)
Country | Project Name | Underground/ | Voltage / Cable Length | Launch/ |
Submarine | Completion | |||
England - | NEMO Link | |||
Belgium | Highest submarine | Submarine | 400 kV / 283 km | May 2019 |
voltage in the world | ||||
India | PK2000 * | Underground | 320 kV / 128 km | March 2021 |
England - | Greenlink * | Submarine | 320 kV / 380 km | Planned for |
Ireland | 2024 | |||
UAE | Lightning | Submarine | 400 kV / 420 km | Planned for |
Highest submarine | ||||
2024 | ||||
voltage in the world | ||||
Germany | Corridor-A (CAN) | 525 kV / 640 km | Planned for | |
Highest voltage in | Underground | |||
2029 | ||||
the world | ||||
Plans of major operators to augment
power grids
■Japan | Source: ENTSO-E (2023), Figure 1.4 |
・Plans to expand the interconnected power grid, mainly
along the Hokkaido → Honshu route.
・OCCTO formulated a master plan in March 2023. Basic requirements will be formulated in FY2023, and public solicitation for operators and selection of suppliers are expected in FY2024 or later. (~FY2050, 8,000 km cable length)
In addition to the track record with NEMO etc., build relationships with European customers.
We've seized the Corridor-A in Germany, and we are currently looking toward future projects.
- Our Initiatives
- Develop insulating material
- Manufacturing a highly insulating compact cable with reversible polarity and heat resistance up to 90 °C is possible.
■Installation method development (cable laying vessel, deep-sea cable laying, protection technique)
■Collaboration with Siemens (cable + transducer)
3-2. DC interconnectors - UK/Germany Market | 5/10 |
We are currently handling DC cable projects in the UK and Germany, where demand is particularly strong.
(1)UK market
■Greenlink overview
・International interconnection line between UK and Ireland. The project is being promoted in a consortium with Siemens of Germany.
Voltage | DC±320kV |
Cable length | Submarine 160 km x 2, Underground 29 km x 2 |
Process | Dec 2021: Order received, 2024: Construction complete |
■UK-Scotland DC interconnection line project
For the purpose of regional power interchange, the construction of a DC transmission network is progressing. (~FY2040, cable length 20,000 km)
(2)German market
■Corridor-A overview
- Project to transmit electricity generated from renewable energy sources in northern Germany to electricity demand areas in the south
DC±525kV | |||
Voltage | World's highest | ||
Our order route | |||
voltage | |||
Corridor-A | |||
Cable | 320 km Underground x |
3 strips (including | |
length | |
neutral lines) | |
Jun 2020: Order | |
Process | received |
2029: Scheduled | |
completion |
■Germany DC interconnection line project
Plans for the development of a large- scale DC power grid for the purpose of transmitting onshore and offshore wind power are progressing.
(~FY2040, 23,000 km cable length)
Source:Amprion -Grid expansion
4. Offshore Wind Power | 6/10 |
The installation of offshore wind power is accelerating. Progress is being made on scaling up the size of wind turbines and power farms.
Capture demand by responding to higher voltage and larger size of cables.
(1) Market Trends | (2)Domestic Major Projects* projects already accepted at our company |
■ Forecast for Offshore Wind Power Installation (Units: GW)
Project Name | Amount (MW) | Period |
*Japan: Offshore General Sea Area
1R+2R: Less than 3 GW
2030 goal: 10 GW
Total |
Americas
Akita Port, Noshiro Port * | 140 | Jan 2023 operation start |
Ishikari Port * | 100 | 2023 scheduled to be |
completed | ||
Goto Sakiyama * | 16 | 2023 scheduled to be |
completed | ||
Asia
China
Europe |
UK |
UK |
- Increasing Turbine Size
10 MW or larger becomes mainstream
Eiffel Tower
North Akita | 480 | 2026-2027 | ||
Yurihonjo | 820 | 2027-2029 | ||
Choshi | 390 | 2026-2027 | ||
(3) Our Initiatives | ||||
■ Technological development | ||||
-Insulating materials | ||||
・water tree retardant | ||||
・Non-cross-linked (environmental | ||||
performance) | ||||
- Dynamic cables (for floating turbines) | ||||
・Twisting/bending/abrasion resistance | ||||
・High voltage (154kV) | ||||
Dynamic | ||||
・Advanced operation system | ||||
Cable | ||||
(Diagnosis of movement and degradation due | ||||
to twisting and flexing)
- Transmission package with Nissin/Densetsu
Source: IEA Offshore Wind Outlook 2019, All rights Reserved. | ・Cable, power receiving, substation and engineering, grid issue | |
⇒ Increased | cable size and voltage | resolution |
5. Overview of New Plant in Scotland | 7/10 |
We will build a new plant for submarine cables in Scotland, UK, where demand is expected to increase dramatically. This will allow us to capture demand for DC interconnectors and offshore wind power around Scotland and the rest of the UK.
- Company Overview
Ross-shire
Scotland
■ Manufactured Products
Name of New | Sumitomo Electric U.K. Power Cables Ltd. | |||
Company | ||||
Location | Ross-shire, Scotland, UK | |||
Business Details | Manufacture and sale of electric power cable | |||
Capital | £127 million | |||
Shareholder Ratio | 100% owned subsidiary | |||
Establishment/ | Established | May 2023; Operation begins September 2026 | ||
Operation | (planned) | |||
Array cables for offshore wind power | Cables for DC interconnectors |
Cables that connect wind turbines to each other and turbines to offshore transformer substations
The grid connections between nations and regions are quickly becoming longer and higher voltage.
The use of DC cables, which have low transmission loss compared to AC cables, is increasing.
turbine offshore land substation
Land Segment | |||
Land Segment | |||
Cable> | |||
Submarine | |||
Segment | Demand |
Area | |
DC Interconnector Cable | Transformer | |
Substation |
(AC) | (DC) | (AC) | ||
Array Cables
(Export Cable)
6. Domestic Power Cable Market | 7. Strengthening manufacturing | 8/10 |
Steady demand for updating aging equipment Aim to ensure demand through long-term partner agreements
Continue to build global manufacturing systems (including in Europe) and expand the production capabilities of the mother factories in Japan throughout the world
-
Market: Introduction of revenue cap system to
promote equipment renewal
(1) Our initiatives
■Safety and environment
1,500 km of OF cable is over 30 years old
Aluminum
Coated
Lead Coated
Subject to renewal
(km)
-Train safe people and build a culture of safety -Reduce CO2 emissions, expand GX products
■Quality
-Own process quality assurance
-Quality assurance function enhancing
(2) Our initiatives
-
Enhance workability and long-term agreements with partners
-Promotinglong-term contracts to secure manufacturing and construction capabilities
-Plan to increase the number of | 2022 2025 2030 |
construction teams to meet increased demand
- Continue introducing distinct products
- Low-losselectric cable; maintenance and monitoring systems
- DLR sensors
■Cost reduction
-Develop new insulating materials
-Improve of overall efficiency of facilities (Reduce outage loss, performance loss, and defective loss)
-Reduce labor (utilize DX)
■Asset efficiency improvement
- Shorten lead times, reduce inventory, and improve CF
8. Conclusion | 9/10 |
Contribute to achieving a carbon-neutral society via the top
technology and manufacturing in the world
DC interconnectors and Offshore Wind Markets: Rapid expansion of installation due to decarbonization
Domestic Power Cable Market: Steady demand for updating aging equipment
・Expanding manufacturing and installation capacity mainly in Europe and Japan (Submarine cable business + Land cable business)
・Development of GX-related products, methods, and systems (DC and offshore) ・Strengthening manufacturing capabilities (quality improvement, cost reduction) ・Strengthening project management
We will advance the above points in efforts to achieve our medium-term targets.
10/10
https://sumitomoelectric.com/
Attachments
- Original Link
- Original Document
- Permalink
Disclaimer
Sumitomo Electric Industries Ltd. published this content on 20 November 2023 and is solely responsible for the information contained therein. Distributed by Public, unedited and unaltered, on 21 November 2023 02:01:09 UTC.