Suzlon Group announced a new order win for the development of a 72.45 MW wind power project for Juniper Green Energy Private Limited. Suzlon will install 23 wind turbine generators (WTGs) with a Hybrid Lattice Tubular (HLT) tower and a rated capacity of 3.15 MW each at the Dwarka district in Gujarat. This order is for the company's larger rated 3.15 MW, S144-140m turbines from the 3 MW product series.

As part of the agreement, Suzlon will supply the wind turbines (equ equipment supply) and execute the project including, erection and commissioning. Suzlon will also undertake comprehensive operations and maintenance services post-commissioning. Suzlon turbines feature the time tested Doubly Fed Induction Generator (DFIG) technology that efficiently integrates wind turbines into the utility network to meet the grid requirements.

Suzlon's R&D efforts are continuously geared towards increasing turbine performance, harnessing more energy from low wind sites, and lowering the cost of energy.