ASX ANNOUNCEMENT
14 February 2022 | ||
only | MOUNT PEAKE PROJECT: DEVELOPMENT UPDATE | |
Key Points | ||
• | TNG continues to advance engineering, permitting, development planning and commercial work streams | |
for its flagship 100%-owned critical and battery minerals project, the Mount Peake Vanadium-Titanium- | ||
Iron Project ("Mount Peake Project" or "Project"), in the Northern Territory. | ||
• | Work undertaken by Clough Projects (Clough) is progressing Stage 2 of the design and value engineering | |
for the integrated mining and processing operation at the Mount Peake mine site ("Mine Site"), together | ||
use | with TNG's Project Team and SMS group. | |
• | The value engineering and design stage is progressing on schedule and is expected to be completed by | |
Clough by the second quarter of 2022. | ||
• | SMS is working to complete any outstanding validation testwork that had been delayed last year due the | |
global COVID-19 restrictions. | ||
• | Hydrogen reduction testwork is currently underway as a suitable replacement for the solid reductant in | |
personal | the current flowsheet. This will further reduce the carbon footprint of the Mount Peake Project and put | |
TNG in a strong position to meet the zero emissions target by 2050. | ||
• | Non-process infrastructure requirements for the integration of the Project at the Mine Site are also well | |
advanced and potential Build Own Operate and Build Own Operate Transfer ("BOO/BOOT proponents are | ||
being targeted. | ||
• | A program of water bore drilling is planned to commence in early April in order to confirm additional water | |
supply for the integrated Mount Peake Project mining operation, beneficiation plant and TIVAN® | ||
processing facility. | ||
• TNG has progressed discussions with its major contractors, including SMS and Clough, to revise and update | ||
the project execution model. This includes a detailed review of the contracting strategy for delivery of both | ||
the processing plants and NPI, early contractor involvement strategies, BOO/BOOT" planning, and the | ||
project management structure. | ||
• | The Company is advancing on a number of technical fronts in order to obtain the information required for | |
the submission of a revised environmental impact report for the integrated Project, following consultation | ||
with the Northern Territory Environmental Protection Authority ("NT EPA"). | ||
For | • | Commodity Markets: Global demand for titanium dioxide and vanadium pentoxide continue to be strong, |
with market prices expected to increase during the year. | ||
Australian resource and mineral processing technology company TNG Limited (ASX: TNG) ("TNG" or the "Company") is pleased to provide an update on the key workstreams being undertaken for the delivery and development of its
100%-owned Mount Peake Vanadium-Titanium-Iron Project ("Mount Peake Project" or "Project"), located in the Northern Territory.
MOUNT PEAKE PROJECT OVERVIEW
The Mount Peake Project is the Company's flagship project, comprising a world-scale critical and battery minerals deposit located 235km north-west of Alice Springs. The Project is well located close to existing key power and transport infrastructure corridors including the Alice Springs-Darwin Railway and the Stuart Highway.
Mount Peake is a shallow, flat-lying orebody with a JORC Measured, Indicated and Inferred Resource totalling 160 million tonnes grading 0.28% V2O5, 5.3% TiO2 and 23% Fe. The Mount Peake Project is one of the largest undeveloped vanadium-titanium-iron projects in the world.
ASX CODE: TNG | REGISTERED OFFICE | T +61 8 9327 0900 | W www.tngltd.com.au |
ABN 12 000 817 023 | Suite 20, 22 Railway Road | F +61 8 9327 0901 | E corporate@tngltd.com.au |
Subiaco, Western Australia 6008 | |||
Validation Testwork
Validation testwork that had been delayed due to the global COVID-19 restrictions affecting workforce availability of SMS staff and the procurement of materials to undertake the testwork is underway.
The validation testwork is being carried out in Australia and Austria, with completion expected to occur in the coming months.
onlyHydrogen Reductant
TNG has assessed opportunities within the Project and the processing flowsheet to reduce the overall net carbon footprint. This includes an ongoing technical and commercial assessment of the use of hydrogen reductant in the current flowsheet. Hydrogen reduction testwork is underway, running in parallel to the current engineering and design work as a potential optimisation initiative.
Non-Process Infrastructure ("NPI")
The new integrated mining and processing operation at the Mount Peake mine site has provided the opportunity usefor consolidation of a number of infrastructure items including power generation, gas supply and communications
installations.
The NPI will require upgrading in a number of areas to support a larger operation, including tendering for village accommodation, camp catering and borefield (water supply).
The Company's Project Team is exploring Build Own Operate and Build Own Operate Transfer ("BOO/BOOT") arrangements, having previously engaged, tendered and shortlisted several proponents and reviewing the NPI for
the Project including updated design and tendering processes as required. The key NPI work streams include:
personalItem
Village
Accommodation
Haul Road
Borefield
Camp Catering
ForCommunications
Materials Handling
Logistics
Power & Gas | Tendered and | Independent power providers previously tendered for two separate |
shortlisted | Build-Own-Operate contracts for the provision of power supply by | |
way of gas fired power stations - for each of the Mine Site and | ||
Darwin Site. |
onlyIn April 2021, TNG's hydrogeological consultants submitted a water extraction licence application ("WELA") for
Water Bore Drilling Program
water supply for the mine site and Beneficiation Plant requirements. This approval is expected imminently.
With the expanded operation, additional water supply will also be required and new program of water bore drilling ("Program") is planned to commence in early April 2022 to establish the availability of additional water supply for the integrated operation. The Program was originally scheduled to start in early March 2022, however it has been
usedelayed due to recent flooding of the areas to be drilled, which has restricted access.
The program, which will be supported by bore pump testing and aquifer modelling and reporting will allow an additional WELA to be submitted. This information will also allow pipeline and water distribution design works and infrastructure to be updated, as well as support and inform the environmental assessment report which is currently in progress.
PROJECT EXECUTION MODEL
The Company has progressed the project execution model to support the delivery of an integrated and mining and
personalprocessing operation at the Mine Site.
TNG is assessing revised proposals from SMS and Clough for the delivery of the Mount Peake Project, while retaining production and product quality guarantees for the downstream processing operation.
The process to update the project execution schedule includes a detailed review of the contracting strategy for delivery of both the processing plants and NPI, early contractor involvement strategies, Build Own Operate and Build Own Operate Transfer ("BOO/BOOT") planning, and project management structure.
The Company expects to finalise a revised project execution model in the coming months.
PERMITTING AND APPROVALS
Environmental
The Northern Territory Environmental Protection Authority ("NT EPA") Referral document for the Mount Peake Processing Project under the Environment Protection Act 2019 indicates that various technical studies require updating as part of the integrated Mount Peake Project, including the following areas:
• | Biological Surveys | |
For | • Groundwater and Surface Water Assessments | |
• | Air Quality Assessment | |
• Greenhouse Gas Assessment and Management Plan | ||
• | Noise Impact Assessment | |
• | Waste Characterisation and Landform Design | |
• | Traffic Impact Assessment | |
• | Stakeholder Engagement Strategy | |
• | Mine Closure Plan |
Scopes of work for the technical studies were developed following consultation with the NT EPA and work has been progressing on these studies with relevant information from the previous Environmental Impact Statement documents for the Mine Site and the Darwin site being utilised to support the updates, where applicable.
5
This is an excerpt of the original content. To continue reading it, access the original document here.
Attachments
- Original Link
- Original Document
- Permalink
Disclaimer
TNG Limited published this content on 13 February 2022 and is solely responsible for the information contained therein. Distributed by Public, unedited and unaltered, on 13 February 2022 22:51:01 UTC.