Total Helium Ltd. announced the start of its first helium and methane sales and provides further updates on its operations at its project in western Kansas where it aims to extend the Hugoton Gas Field, the larger conventional onshore natural gas and helium field in North America. First Operational Disposal Well: Miller 9C: Miller 9C has been drilled and completed. The well is operational and receiving produced water from the Miller 9D well.

Completion of Boltz 35B: The production testing for the well is being conducted in two stages. As part of the first stage, the experimental lower zone was stimulated first. Total Helium is now preparing the stimulation of original target upper zones, which are similar to the Miller 9D well.

The production from all zones is expected in the upcoming month.