Total Helium Ltd. provides an operational update on its Pinta South Project. Pipeline Construction Underway, Wells Hooked to Processing Facility: As part of Total Helium's acquisition of the Pinta South Project in Arizona, Total Helium acquired a 20% working interest in 2 producing wells and a 50% working interest in 27,000 acres which includes 8 additional wells that are awaiting connection to the helium processing facility. Total Helium has constructed a six mile pipeline and has connected 5 of those 8 wells to the helium processing facility.

3 Additional Wells Drilled: In addition to the 10 wells that Total Helium initially acquired, in the last two weeks an additional 3 wells have now been drilled and are awaiting completion. Initial Soil Gas Survey Completed, Follow Up Study Underway: An effort is underway to optimize drilling locations by conducting an additional helium soil sample survey. Previous surveys have shown promising results that indicated the presence of several anomalies to help delineation of sand channels/river systems. Although Total Helium's drilling program anticipates most wells will be drilled and completed within the blanket Shinarump formations, "sand channel" wells are expected to enhance production rates.

The 20% owned two producing wells are "sand channel" wells and have produced 243,700 MCF (28-1 NS Well) and 179,000 MCF (27-1 NS Well) with 8% helium over the past three years. As warmer, dryer weather has arrived in Arizona, Total Helium and its joint venture partner have begun the helium soil sampling survey to identify these channel systems. The soil gas survey will run from mid-May through early June 2023.