JOINT TECHNICAL STUDY BLOCK SK334, ONSHORE SARAWAK Monthly Progress Report for Shareholders
(Ending January 2023) | Page1of 1 |
Objectives of SK334 Joint Technical Study
- Assess hydrocarbon potential and generate leads and prospects;
- High grade and delineate prospective areas; and
- Design new seismic acquisition plan and/or other feasible exploration tools for execution in future De-risking activities.
Project Progress Update
Progress to Date / Milestone Achieved:
- Concluded market survey & screening exercise on seismic data processing on the 25th January 2023. 9 companies invited, out of which 6 companies responded and submitted.
- Geological Study:
- Ongoing regional and local geology analysis.
- Submitted Geological Fieldwork Plan to PETROS. The Plan was accepted and agreed by PETROS.
- Geological fieldwork planned to be conducted on 16 - 24 February 2023.
- Geophysical Study:
- Seismic interpretation works ongoing: 4 regional horizons completed. Fault interpretation and detailing ongoing.
- Data preparation and integration for FTG evaluation on structural styles, major & minor fault lineaments mainly in areas void of seismic.
- FTG Study:
- Completed 'inversion' work prior to data modelling.
Opportunities, Issues & Challenges:
- Nil
Forward Plan:
- Detailing leads and prospects mapping.
- Velocity analysis and time-to-depth conversion on structure maps.
- Continuation of integrated geological and geophysical works.
- FTG data modelling, interpretation and integration data with geology (fieldwork), SAR and seismic as work progresses.
- Progress Meeting with PETROS is scheduled in middle of March 2023.
Project Details
Block Name | SK334, Onshore Sarawak |
Block Size | 6,685 sq.km |
Start/Completion Date | Sept 2022 / Nov 2023 |
Project Duration | 15 months |
Key Project Team Members
Managing Director | DBD |
Team Leader | FW |
Project Advisor | AD |
Corporate Advisor | GM |
Head, Geoscience | AK |
Geoscience Advisor | NT |
Geoscience Advisor | Professor Dr AH |
Principal Geologist | JAN |
Principal Geophysicist | SH |
FTG Expert | Dr AB |
Geochem Expert | Dr KM |
Senior Geologist | RB |
Senior Geologist | Dr LL |
Reservoir Engineer | GC |
Front End Engineer | AZ |
Head, Admin | FI |
Engineer | MJ |
Engineer | IN |
Liaison Officer | KA |
Local Coordinator | R @ NS |
Legal Advisor | MBNA Solicitors & Advoc. |
2022 | 2023 | ||||||||||||||
Petroleum Activities & Timeline | |||||||||||||||
1 | 2 | 3 | 4 | 5 | 6 | 7 | 8 | 9 | 10 | 11 | 12 | 13 | 14 | 15 | |
S | O | N | D | J | F | M | A | M | J | J | A | S | O | N | |
General & Administration
Agreement Signing
Review of all available data/reports
Geophysical Studies
2D seismic reprocessing
FTG and Magnetic data review and interpretation
Plan | Actual |
Geological studies
Project database setup and review
Geoscience integrated interpretation (using Petrel)
Fieldwork analogue survey
Basin modelling and structural balancing and restoration
Play identification and prospect analysis
Engineering & Economics
Conceptual Field Development Plan
Petroleum Economics
Prepared by Upland Big Oil Sdn Bhd
Attachments
- Original Link
- Original Document
- Permalink
Disclaimer
Upland Resources Ltd. published this content on 17 February 2023 and is solely responsible for the information contained therein. Distributed by Public, unedited and unaltered, on 17 February 2023 14:05:06 UTC.