Objectives of SK334 Joint Technical Study

  1. Assess hydrocarbon potential and generate leads and prospects;
  2. High grade and delineate prospective areas; and
  3. Design new seismic acquisition plan and/or other feasible exploration tools for execution in future De-risking activities.

Project Progress Update

Progress to Date / Milestone Achieved:

  • Geological & Geophysical Study:
    • Technical Discussion and Workstation Review was successfully conducted with Joint Technical Study (JTS) members from Petroleum Sarawak Berhad (PETROS) on the 13th July 2023. Among others, seismic reprocessing result, prospect/lead maps, FTG remodeling result integration works, and resources assessment methodology were discussed and deliberated. The objectives of the technical discussion were met.
    • Updated deterministic and probabilistic HC resource assessment.
    • Commenced planning of future exploration works in Limbang and Lawas, as part of PSC preparation.
  • Conceptual Engineering:
    • HC evacuation plan identified and shortlisted. Continuation of notional field development plan.

Opportunities, Issues & Challenges:

  • Met with Petroleum Authority of Brunei (PAB) on the 11th July 2023 and requested access to data of neighboring blocks in Onshore Brunei, including well log reports and seismic data, to provide better understanding of SK334 prospectivity.
  • Met with Brunei Energy Services and Trading (BEST) on the 12th July 2023 to discuss potential collaboration during PSC stage.
  • Rig visit and meeting with rig contractor on the 25th July 2023, as part of onshore drilling rig technical and commercial market assessment.

Forward Plan:

  • Continuation of conceptual field development plan.
  • Technical Workshop with PETROS is planned on the 17th August 2023.

Project Details

Block Name

SK334, Onshore Sarawak

Block Size

6,685 sq.km

Start/Completion Date

Sept 2022 / Nov 2023

Project Duration

15 months

Key Project Team Members

Managing Director

DBD

Team Leader

FW

Project Advisor

AD

Corporate Advisor

GM

Head, Geoscience

AK

Geoscience Advisor

NT

Geoscience Advisor

Professor Dr AH

Principal Geologist

JAN

Principal Geophysicist

SH

FTG Expert

Dr AB

Geochem Expert

Dr KM

Senior Geologist

RB

Senior Geologist

Dr LL

Reservoir Engineer

GC

Front End Engineer

AZ

Head, Admin

FI

Engineer

MJ

Engineer

IN

Liaison Officer

KA

Local Coordinator

R @ NS

Legal Advisor

MBNA Solicitors & Advoc.

2022

2023

Petroleum Activities & Timeline

1

2

3

4

5

6

7

8

9

10

11

12

13

14

15

S

O

N

D

J

F

M

A

M

J

J

A

S

O

N

General & Administration

Agreement Signing

Review of all available data/reports

Geophysical Studies

2D seismic reprocessing

FTG and Magnetic data review and interpretation

Plan

Actual

Geological studies

Project database setup and review

Geoscience integrated interpretation (using Petrel)

Fieldwork analogue survey

Basin modelling and structural balancing and restoration

Play identification and prospect analysis

Engineering & Economics

Conceptual Field Development Plan

Petroleum Economics

Prepared by Upland Big Oil Sdn Bhd

JOINT TECHNICAL STUDY BLOCK SK334, ONSHORE SARAWAK Monthly Progress Report for Shareholders

(Ending July 2023)

Page2of 3

ATTACHMENT(S)

Pictures from the Technical Discussion and Workstation Review that was successfully conducted with JTS members from Petroleum Sarawak Berhad (PETROS) on the 13th July 2023 at Upland Big

Oil's office. The Workshop was attended by 4 personnel from PETROS.

Prepared by Upland Big Oil Sdn Bhd

JOINT TECHNICAL STUDY BLOCK SK334, ONSHORE SARAWAK Monthly Progress Report for Shareholders

(Ending July 2023)

Page3of 3

ATTACHMENT(S)

Pictures from the Rig Site Visit and Meeting with Rig Contractor in Perth on the 25th July 2023.

Prepared by Upland Big Oil Sdn Bhd

Attachments