VRX Silica Limited provided an update on progress at its Arrowsmith North Silica Sand Project. The company has commenced drilling of a water production bore which will be the source of water supply for the proposed processing plant at Arrowsmith North. Drilling is being undertaken by a licenced water bore driller, under an approved Licence to Construct or Alter a Well, CAW205840(1), from the Department of Water and Environmental Regulation (DWER). DWER has accepted the company's application for an allocation of 900,000 kilolitres. The 5C licence to take water will be applied for once the bore is constructed, and logging and testpumping is complete.